Method of findingthe dry ingredient quantity of 1 m3
concrete.
Answer Posted / b.subhash
Estimating Quantities of material needed.
1. Calculate the volume of concrete needed.
2. Estimate the total volume of dry material by
multiplying the required volume of concrete by 1.65 to get
the total volume of dry loose material needed (this includes
10% extra to compensate for losses).
3. Add the numbers in the volumetric proportion that you
will use to get a relative total. This will allow you later
to compute fractions of the total needed for each
ingredient. (i.e. 1:2:4 = 7).
4. Determine the required volume of cement, sand and
gravel by multiplying the total volume of dry material (Step
2) by each components fraction of the total mix volume (Step
3) i.e. the total amount cement needed = volume of dry
materials * 1/7.
5. Calculate the number of bags of concrete by dividing
the required volume of cement by the unit volume per bag of
cement (0.0332 m3 per 50 kg bag of cement or 1 ft3 per 94 lb
bag).
For example, for a 2 m x 2 m x 10 cm thick pump pad:
1. Required volume of concrete = 0.40 m3
2. Estimated volume of dry material = 0.4 x 1.65 = 0.66 m3
3. Mix totals = 1+2+4 = 7 (1:2:4 cement:sand:gravel)
4. Ingredient Volumes: 0.66 x 1/7 = .094 m3 cement
0.66 x 2/7 = .188 m3 sand
0.66 x 4/7 = .378 m3 gravel
5. # Bags of cement: 0.094 m3 cement / .0332 m3 per 50 Kg bag
= 2.83 bags of cement (use three bags)
Is This Answer Correct ? | 158 Yes | 44 No |
Post New Answer View All Answers
a butt weld is specified by
what is the minimum cement content for M20 & M25 as per is code -456(2000).
What is the ideal size of the living room ranges from small to large size?
In Residential home construct footing,beam, column,lintel,rcc roofs which dia rod used how to self assumed
Which is the latest version of solidsworks?
How to calculate paint drums per meter square
What is the tallest man made structure in the world?
What are the applications of cad?
HOW TO CLACULATE CEMENT AND SAND CONSUMPTION FOR THE STAIRCASE KOTA FLOORING IN THE RATIO OF 1:4 50 MM THICKNESS
it is a corrected question." make a list of engineering property(properties) of soil.
what is the coefficient for running feet to cft coversion both area and price
pls tell estimate for 1 kilometre length random rubble masonry 0.90 metre height 0.600 metre width
Can anybody explain with the help of sketeches that what are 2legged , four legged & 6legged stirrups and how to calculate cut length of diamond ring(stirrups)?
What is the difference between absorption & adsorption and sorption?
PLS.......... ANY ONE CAN FORWARD ME PREVIOUS QUESTION PAPER hpcl civil engg