Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

Method of findingthe dry ingredient quantity of 1 m3
concrete.

Answer Posted / b.subhash

Estimating Quantities of material needed.

1. Calculate the volume of concrete needed.
2. Estimate the total volume of dry material by
multiplying the required volume of concrete by 1.65 to get
the total volume of dry loose material needed (this includes
10% extra to compensate for losses).
3. Add the numbers in the volumetric proportion that you
will use to get a relative total. This will allow you later
to compute fractions of the total needed for each
ingredient. (i.e. 1:2:4 = 7).
4. Determine the required volume of cement, sand and
gravel by multiplying the total volume of dry material (Step
2) by each components fraction of the total mix volume (Step
3) i.e. the total amount cement needed = volume of dry
materials * 1/7.
5. Calculate the number of bags of concrete by dividing
the required volume of cement by the unit volume per bag of
cement (0.0332 m3 per 50 kg bag of cement or 1 ft3 per 94 lb
bag).

For example, for a 2 m x 2 m x 10 cm thick pump pad:

1. Required volume of concrete = 0.40 m3
2. Estimated volume of dry material = 0.4 x 1.65 = 0.66 m3
3. Mix totals = 1+2+4 = 7 (1:2:4 cement:sand:gravel)
4. Ingredient Volumes: 0.66 x 1/7 = .094 m3 cement
0.66 x 2/7 = .188 m3 sand
0.66 x 4/7 = .378 m3 gravel
5. # Bags of cement: 0.094 m3 cement / .0332 m3 per 50 Kg bag
= 2.83 bags of cement (use three bags)

Is This Answer Correct ?    158 Yes 44 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

why should we use 20mm graded metal only in vrcc?why we shouldnot use 40mm metal?

11186


natucher of concrete &type of concrete?

2431


why top layer of block work shoud be full size if any cut block adjustable than another layer?

2206


what is polity

2116


how to read the drawings to find the quantity of steel in a storm water manhole or any other structure?

2599


20 mpa what is the quantity of cement sand and aggregate in one cubic meter of pcc non rainforcement concreate kindly answer including formaula thanks

2733


What is the amount of work done by a carpenter, bar Bender and plaster Mason in interior and exterior plaster

2315


What is difference between combin footing & rapt footing

1940


How to calculate the area in squarefeets ?How much area of sqft for this measurements?East 53.3ft West 54ft North 47.7ft South 51.1ft ?

1954


how much quantity of 1.5" nails and 2.5" nails are required for conventional formwork shuttering?

1684


Define Who designed the city of Washington DC?

1108


what is the price of a cubic meter of concrete on international market?

1224


what is concrete canvas?

2302


What is the significance of cost estimate knowledge for an architect?

1664


hi every body..i have applied for RRB section engineers CIVIL.i wanna prepare for that,so can any one suggest me some books and where can i get the syllabus for this..i would be vry greatful if any one can help in this regard

2107