Question { DELL, 11117 }

I have 5 sessions s1,s2,s3,s4 & s5 and i want execute
s1,s2,s3,s5 after s4. How?


Answer

Quest:my question is first execute s1,s2,s3,s5 after that
execute s4?

Ans:if the s4 execution is depends on all the previous
session then use decision task . Put the status=succeeded .
If all the four sessions executed successfully then S4 will
execute.