While reviewing an ongoing project, the IS auditor notes that the development team has spent eight hours of activity on the first day against a budget of 24 hours (over three days). The projected time to complete the remainder of the activity is 20 hours. The IS auditor should report that the project:

A. is behind schedule.

B. is ahead of schedule.

C. is on schedule.

D. cannot be evaluated until the activity is completed.



While reviewing an ongoing project, the IS auditor notes that the development team has spent eight h..

Answer / chatter

The correct answer is A

A. Earned value analysis (EVA) is based on the premise that if a project task is assigned 24 hours for completion, it can be reasonably completed during that time frame. According to EVA, the project is behind schedule because the value of the eight hours spent on the task should be only four hours, considering that 20 hours of effort remain to be completed.

B. The project is not ahead of schedule because the work remaining exceeds the time allotted.

C. The project is not on schedule because only 16 hours remain to do 20 hours work.

D. The amount of work left has been evaluated at 20 hours and the time left on the project is 16 hours, so the auditor can evaluate the current status of the project.

Question #: 318 CISA Job Practice Task Statement: 3.4

Is This Answer Correct ?    5 Yes 0 No

Post New Answer

More CISA Certification Interview Questions

During an IT audit of a large bank, an IS auditor observes that no formal risk assessment exercise has been carried out for the various business applications to arrive at their relative importance and recovery time requirements. The risk that the bank is exposed to is that the: A. business continuity plan may not have been calibrated to the relative risk that disruption of each application poses to the organization. B. business continuity plan may not include all relevant applications and therefore may lack completeness in terms of its coverage. C. business impact of a disaster may not have been accurately understood by the management. D. business continuity plan may lack an effective ownership by the business owners of such applications.

1 Answers  


IS auditors, in performing detailed network assessments and access control reviews should FIRST: A. determine the points of entry. B. evaluate users access authorization. C. assess users identification and authorization. D. evaluate the domain-controlling server configuration.

2 Answers  


Which of the following is the MOST fundamental step in effectively preventing a virus attack? A. Executing updated antivirus software in the background on a periodic basis B. Buying standard antivirus software, which is installed on all servers and workstations C. Ensuring that all software is checked for a virus in a separate PC before being loaded into the production environment D. Adopting a comprehensive antivirus policy and communicating it to all users

1 Answers  


When reviewing a service level agreement for an outsourced computer center an IS auditor should FIRST determine that: A. the cost proposed for the services is reasonable. B. security mechanisms are specified in the agreement. C. the services in the agreement are based on an analysis of business needs. D. audit access to the computer center is allowed under the agreement.

1 Answers  


In a risk-based audit approach, an IS auditor, in addition to risk, would be influenced by: A. the availability of CAATs. B. management's representation. C. organizational structure and job responsibilities. D. the existence of internal and operational controls

2 Answers  






Which of the following functions would be acceptable for the security administrator to perform in addition to his/her normal functions? A. Systems analyst B. Quality assurance C. Computer operator D. Systems programmer

1 Answers  


Which of the following tasks is performed by the same person in a well-controlled information processing facility/computer center? A. Security administration and management B. Computer operations and system development C. System development and change management D. System development and systems maintenance

1 Answers  


Which of the following activities should the business continuity manager perform FIRST after the replacement of hardware at the primary information processing facility? A. Verify compatibility with the hot site. B. Review the implementation report. C. Perform a walk-through of the DRP. D. Update the IS assets inventory.

1 Answers  


Before reporting results of an audit to senior management, an IS auditor should: A. Confirm the findings with auditees. B. Prepare an executive summary and send it to auditee management. C. Define recommendations and present the findings to the audit committee. D. Obtain agreement from the auditee on findings and actions to be taken.

1 Answers   TPA,


A dry-pipe fire extinguisher system is a system that uses: A. water, but in which water does not enter the pipes until a fire has been detected. B. water, but in which the pipes are coated with special watertight sealants. C. carbon dioxide instead of water. D. halon instead of water.

1 Answers  


The most common reason for the failure of information systems to meet the needs of users is that: A. user needs are constantly changing. B. the growth of user requirements was forecast inaccurately. C. the hardware system limits the number of concurrent users. D. user participation in defining the system's requirements was inadequate.

1 Answers  


Which of the following is MOST effective in controlling application maintenance? A. Informing users of the status of changes B. Establishing priorities on program changes C. Obtaining user approval of program changes D. Requiring documented user specifications for changes

1 Answers  


Categories
  • Cisco Certifications Interview Questions Cisco Certifications (2321)
  • Microsoft Certifications Interview Questions Microsoft Certifications (171)
  • Sun Certifications Interview Questions Sun Certifications (45)
  • CISA Certification Interview Questions CISA Certification (744)
  • Oracle Certifications Interview Questions Oracle Certifications (64)
  • ISTQB Certification Interview Questions ISTQB Certification (109)
  • Certifications AllOther Interview Questions Certifications AllOther (295)