Which of the following would an IS auditor expect to find in
a console log?

A. Names of system users

B. Shift supervisor identification

C. System errors

D. Data edit errors



Which of the following would an IS auditor expect to find in a console log? A. Names of system u..

Answer / guest

Answer: C

System errors are the only ones that you would expect to
find in the console log.

Is This Answer Correct ?    4 Yes 1 No

Post New Answer

More CISA Certification Interview Questions

Which of the following steps would an IS auditor normally perform FIRST in a data center security review? A. Evaluate physical access test results. B. Determine the risks/threats to the data center site. C. Review business continuity procedures. D. Test for evidence of physical access at suspect locations.

1 Answers  


When developing a risk-based audit strategy, an IS auditor should conduct a risk assessment to ensure that:

6 Answers  


After implementation of a disaster recovery plan (DRP), pre-disaster and post-disaster operational cost for an organization will: A. decrease. B. not change (remain the same). C. increase. D. increase or decrease depending upon nature of the business.

1 Answers  


Which of the following statements relating to packet switching networks is CORRECT? A. Packets for a given message travel the same route. B. Passwords cannot be embedded within the packet. C. Packet lengths are variable and each packet contains the same amount of information. D. The cost charged for transmission is based on packet, not distance or route traveled.

1 Answers   Karura Community Chapel,


When an IS auditor obtains a list of current users with access to a WAN/LAN and verifies that those listed are active associates, the IS auditor is performing a: A. compliance test. B. substantive test. C. statistical sample. D. risk assessment.

1 Answers  






Which of the following provides the framework for designing and developing logical access controls? A. Information systems security policy B. Access control lists C. Password management D. System configuration files

2 Answers  


Which of the following tests performed by an IS auditor would be the MOST effective in determining compliance with an organization's change control procedures? A. Review software migration records and verify approvals. B. Identify changes that have occurred and verify approvals. C. Review change control documentation and verify approvals. D. Ensure that only appropriate staff can migrate changes into production.

1 Answers  


The MAIN reason for requiring that all computer clocks across an organization be synchronized is to: A. prevent omission or duplication of transactions. B. ensure smooth data transition from client machines to servers. C. ensure that email messages have accurate time stamps. D. support the incident investigation process.

2 Answers  


During a review of a customer master file an IS auditor discovered numerous customer name duplications arising from variations in customer first names. To determine the extent of the duplication the IS auditor would use: A. test data to validate data input. B. test data to determine system sort capabilities. C. generalized audit software to search for address field duplications. D. generalized audit software to search for account field duplications.

1 Answers  


Separation of duties between computer opeartors and other data processing personnel is intended to: A. Prevent unauthorized modifications to program or data. B. Reduce overall cost of operations C. Allow operators to concentrate on their assigned duties D. Restrict operator access to data

2 Answers  


Which of the following BEST describes an IT department?s strategic planning process? A. The IT department will have either short-range or long-range plans depending on the organization?s broader plans and objectives. B. The IT department?s strategic plan must be time and project oriented, but not so detailed as to address and help determine priorities to meet business needs. C. Long-range planning for the IT department should recognize organizational goals, technological advances and regulatory requirements. D. Short-range planning for the IT department does not need to be integrated into the short-range plans of the organization since technological advances will drive the IT department plans much quicker than organizational plans.

1 Answers  


Which of the following processes is the FIRST step in developing a business continuity and disaster recovery plan for an organization? A. Alternate site selection B. Business impact analysis C. Test procedures and frequency D. Information classification

1 Answers  


Categories
  • Cisco Certifications Interview Questions Cisco Certifications (2321)
  • Microsoft Certifications Interview Questions Microsoft Certifications (171)
  • Sun Certifications Interview Questions Sun Certifications (45)
  • CISA Certification Interview Questions CISA Certification (744)
  • Oracle Certifications Interview Questions Oracle Certifications (64)
  • ISTQB Certification Interview Questions ISTQB Certification (109)
  • Certifications AllOther Interview Questions Certifications AllOther (295)