If inadequate, which of the following would be the MOST
likely contributor to a denial-of-service attack?
A. Router configuration and rules
B. Design of the internal network
C. Updates to the router system software
D. Audit testing and review techniques
Answers were Sorted based on User's Feedback
Answer / guest
Answer: A
Inadequate router configuration and rules would lead to an
exposure to denial-of-service attacks. Choices B and C would
be lesser contributors. Choice D is incorrect because audit
testing and review techniques are applied after the fact.
| Is This Answer Correct ? | 6 Yes | 0 No |
Which of the following would be considered a business risk? A. Former employees B. Part-time and temporary personnel C. Loss of competitive edge D. Hackers
Which is the first software capability maturity model (CMM) level to include a standard software development process? A. Initial (level 1) B. Repeatable (level 2) C. Defined (level 3) D. Optimizing (level 5)
Which of the following is a management technique that enables organizations to develop strategically important systems faster while reducing development costs and maintaining quality? A. Function point analysis B. Critical path methodology C. Rapid application development D. Program evaluation review technique
Which of the following is the MOST important function to be performed by IS management when a service has been outsource? A. Ensuring that invoices are paid to the provider B. Participating in systems design with the provider C. Renegotiating the provider's fees D. Monitoring the outsourcing provider's performance
Which of the following is a benefit of using callback devices? A. Provide an audit trail B. Can be used in a switchboard environment C. Permit unlimited user mobility D. Allow call forwarding
When two or more systems are integrated, input/output controls must be reviewed by the IS auditor in the: A. systems receiving the output of other systems. B. systems sending output to other systems. C. systems sending and receiving data. D. interfaces between the two systems.
Which of the following goals would you expect to find in an organization's strategic plan? A. Test a new accounting package. B. Perform an evaluation of information technology needs. C. Implement a new project planning system within the next 12 months. D. Become the supplier of choice within a given time period for the product offered.
An IS auditor needs to link his/her microcomputer to a mainframe system that uses binary synchronous data communications with block data transmission. However, the IS auditor's microcomputer, as presently configured, is capable of only asynchronous ASCII character data communications. Which of the following must be added to the IS auditor's computer to enable it to communicate with the mainframe system? A. Buffer capacity and parallel port B. Network controller and buffer capacity C. Parallel port and protocol conversion D. Protocol conversion and buffer capability
Which of the following development methods uses a prototype that can be updated continually to meet changing user or business requirements? A. Data-oriented development (DOD) B. Object-oriented development (OOD) C. Business process reengineering (BPR) D. Rapid application development (RAD)
An organization is proposing to install a single sign-on facility giving access to all systems. The organization should be aware that: A. Maximum unauthorized access would be possible if a password is disclosed. B. User access rights would be restricted by the additional security parameters. C. The security administrator?s workload would increase. D. User access rights would be increased.
Which of the following risks would be increased by the installation of a database system? A. Programming errors B. Data entry errors C. Improper file access D. Loss of parity
Many IT projects experience problems because the development time and/or resource requirements are underestimated. Which of the following techniques would provide the GREATEST assistance in developing an estimate of project duration? A. Function point analysis B. PERT chart C. Rapid application development D. Object-oriented system development