Answer Posted / mads
Entry criteria is what has been agreed by relevant parties
as to what needs to be completed before a particular phase
of testing can begin. This can include fully documented
release notes, completion of other test phases etc. Exit
criteria is what needs to be completed before a test phase
can finish. This can mean a certain percentage of test
coverage, or based on there being only X number of critical
bugs. Hope this helps further
| Is This Answer Correct ? | 6 Yes | 1 No |
Post New Answer View All Answers
How do you get programmers to build testability support into their code?
explain ur testing project? how can u nexplain . what should we explain ? i have not worked on any project?
Hi could some one please send me the testplan testcases(for 2Modules) and testscripts for mercry fliht aplication or gmail. please write those on templates and send me.In testplan plase write Testobjective, test scope, est approach, exlusions assumptios.
Could anyone share FAQs for Test Manager position...
What was a problem you had in your previous assignment (testing if possible)? How did you resolve it?
Explain Operational Acceptance Testing with example ?
Define cause effect graphing?
why QA team is necessary for an organization?
When we are recording in WinRunner and interact with the AUT, what does WinRunner do?
What is early testing?
Why would we not include these?
What is agile testing and why is it important?
could anyone explain application testing in sequence order i don't have any experience in that
Why do we need different environments and different data? What is the other name for environment? Justify your explanation ? real time experts pls xplain?
Which is the best testing model?