What are the values of NUM1 and NUM2 after executing the
following code?
CLONO1NO2NO3 Factorl÷÷+OpcdeFactor2+÷+ResultLenDHHiLoEq
C MOVE *LOVAL NUM1 50
C MOVE *J-fIVAL NtJM2 52
Answer Posted / manish verma
The correct question should be:--
CLONO1NO2NO3 Factorl÷÷+OpcdeFactor2+÷+ResultLenDHHiLoEq
C MOVE *LOVAL NUM1 50
C MOVE *HIVAL NUM2 52
and the answer will be
num1= -99999
num2= 999.99
Conclusion is that whatever the size of the variable that
much 9's will be filled with (-)ve value for loval and
wuith (+)ve value for hival.
| Is This Answer Correct ? | 12 Yes | 0 No |
Post New Answer View All Answers
what is data area and how it is used in rpg program ?
Suppose we have one database file and it is used by 5 programs and in 3 program we have to add some records in datbase file s what is the impact on other program?
what is the procedure and explain about real time scenario.
Hi Viewers can any body explain me how to update and ahange the already existed data in physical file using subfile ? please explain me with the code if possible?
Please tell me how to read the records from a file with load an array of size with error conditions(The logic answer for this question is ARR is array of 99 elements Z-ADD 0 IDX *LOVAL SETLL FILE READ FILE 99 *IN99 DOWEQ *OFF IDX ANDLT 99 ADD 1 IDX MOVE FIELD ARR,IDX READ FILE 99 ENDDO).So,Please give me the complete of this code.
Q:Hi all,i want accurate answer with code using in built functions.please sent me code as soon as posible. I have program nmed PGM1 which '' RETRIEVE Current production date''should correctly default the production date for the user who is issuing raw materials to the manufacturing.The production date can be different from the celendra date. However, the program does not make the correct adjustment for all manufacturing plants. there is a parameter which determines the production start time e.g. 07:00 if the system time precedes this,the program subtracts one from the celendra day.This work fine when the celendar day starts after production day as it does in England,the system should be adding one to the celendar day during the overlap. unfortunately the program was desined to assumed the celendar day always starts before the production day. Change required in the program: Change the PROGRAM PGM1 to use the new parrameter to decide whether to add or subtract 1 from the celendar day when determining the production date.
what is file information data structure?
If my rpg program has a date field, what extra care I have to take while compiling that rpg program? If the file is keyed and I have declared the file as well as key list properly in my program. Still am getting an error message like "chain/reade operation is not allowed" what may be the case?
can anybody help me to solve this problem. the program that i m checking display error message saying "Record format for file AJDSPFFD does not match model file and decimal error. how to solve this problem. The AJDSPFFD is snapshot the AJTLOG that is the audit trail list.
what is the necessary keyword needed to scroll subfile records?
How to declare the pull button in AS/400..
what happens when sflsiz = sflpag? What are the advantages and disadvantages?
How would display prime numbers using CL program?
Q:HI friends accually ihave one problem plesase let me know the alternate code of this code. Related field description of code: Add a field, CALvsPRD, "Calendar Day Starts Before/After Production Day" to the parameter set WRKORDER which accepts values 'A' or 'B' o B = Calendar Day Starts Before Production Day o A = Calendar Day Starts After Production Day o Any other value indicates the production and calendar dates are always the same. code: Automatic Execution Of *INZSR Subroutine /Z01 * retrieves WRKORDER field values. /Z01 * Calculate default Production Date and return it to caller. /Z01 * Production date defaults to system date /Z01 C Eval P@Pdate = %DATE() /Z01 * unless Calendar date starts Before PDN(production) date and /Z01 * system time is before PDN Start Time then /Z01 * PDN date is yesterday. /Z01 C If W@CALvsPRD = 'B' and /Z01 C %TIME() < %TIME (W@Strtime) /Z01 C Eval P@Pdate -= %Day(1) /Z01 * unless Calendar date starts After PDN date and /Z01 * system time is *GE PDN(production) Start Time then /Z01 * PDN date is tomorrow. /Z01 C ElseIf W@CALvsPRD = 'A' and W@Strtime > *Zero and /Z01 C %TIME() >= %TIME (W@STrtime) /Z01 C Eval P@Pdate += %Day(1) /Z01 C EndIf /Z01 C Eval *InLr = *On
how do you use commitment control in rpg?