How is a shelf-life item managed in SAP? What is the full cycle?
Answer Posted / saurabh patil
Shelf life data maintained in plant data view 1 in material master
there are 2 fields
1 Total Shelf Life - Lets assume is 30 days.
Then GR data is production date and
GR+30 days is expiration date
Lets assume not maintained.
Date in GR is considered expiration date
2 Minimum remaining shelf life
The minimum remaining shelf life for the system to accept GR of the material.
Lets assume this vale is 15 and the material arrives with shelf life expiring in 10 days . Then system will not accept GR.
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
Mention the document types that are used in purchase requisition?
What is the last step in the procurement cycle?
What are the month end activities in sap mm?
Explain vendor return procedure and its mapping in sap?
What are the components of the master data that details a companys procurement used by, vendor evaluation for example?
Explain the types of consignement stocks in sap mm
Hi , anyone please clear my doubt. we maintain Price in MM and PIR , suppose if price changes we will update in PIR and also changes in PO ,do we need to update in MM?, if we update, where MM Price is reflected?
Can forecast model be selected automatically?
Outline the functions supported by material master?
How is the inventory management integrated with mm?
What is batch information cockpit?
What is purpose of zgr based invoice verification in purchase order?
How to delete a material completely?
What are the important steps in the procurement life cycle?
What are the mrp procedures available in mm-cbp (consumption based planning)?