Method of findingthe dry ingredient quantity of 1 m3
concrete.
Answer Posted / waqas ahmad
it is the 54% of dry volume
1m3 wet volume = 54% dry volume
1 :1.5 : 3
1+(54%) x 1= 1+0.54 = 1.54
cement = (1x1.54) / 5.5
sand = (1.5x1.54) /5.5
aggregate = (3x1.54) /5.5
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
Draw a neat sketch showing the 'throat' of a welding in a plate girder ?
pls send me interview question paper with answer of EIL/AAI/UPSC/RPSC because i am doing prepration of compitation exam of UPSC for the Asst. Executive Engineer
can u plz send me ntpc placement papers(civil engineering) at mohit_verma21@yahoo.com
plz.show development and anchorage length in simple diagram.
What is the per cu. mt. price of ready mix in Gujarat region.?
i want to ecil (Electronics Corporation of India Limited Hyderabad) previous civil engineering question papers immediately please.............
please send me bhel questions on rupesh.017@rediffmail.com
please send latest placement papers of hpcl officers trainee test. i will be very thankful to you.
can any one give me sample question paper of BHEL at mdansari86@gmail.com as i m appearing for the same exam.
PLS.......... ANY ONE CAN FORWARD ME PREVIOUS QUESTION PAPER hpcl civil engg
HOw much % of premium on DSR-2013 currently
I need to constructive work in amaraj batteries
Anyone have sample questions for bhel interview.please send me as Iam appearing for the interview on 19th sep2008. Kindly send this to my e-mail: arun_prasath_n@yahoo.co.in
Kindly post me previous year interview questions with answer for post of DY. Manager (civil engg.) for GAIL, NTPC, IOC, OIL and ONGC etc.
In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting? 2nd :- I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?