Method of findingthe dry ingredient quantity of 1 m3
concrete.
Answer Posted / waqas ahmad
it is the 54% of dry volume
1m3 wet volume = 54% dry volume
1 :1.5 : 3
1+(54%) x 1= 1+0.54 = 1.54
cement = (1x1.54) / 5.5
sand = (1.5x1.54) /5.5
aggregate = (3x1.54) /5.5
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
to minimize budget cost of building , what can i do
when it is noted "JAMB SIM" what is the term "SIM" and what does it mean?
what is the max. and mim. height of vertical post in informatry sign board which is used in highway projects.
Define What is the force exerted by the Tacoma narrows bridge?
What are the advantages of cad software?
What is the difference in painting using Roller and Brush? What is the paint consumption difference? As per IS one coat of painting is painting from left to right and top to bottom whether this can be done using roller ( Roller Stick height and feasibility) ?
How to calculate the load of partion in flat slab if we use brick?
what is smart building materials?
Which code is used for tor & tmt steel bar?
Rate analysis of 150mm, 100mm, & 230mm thk BBM work
how do we design mix ratio?
Design a shear wall of length 4.20 m and thickness of 250mm subjected to the following forces.Assume Fck = 25Mpa and Fy = 415Mpa and the wall is a high wall with central part 3440mm x 250mm and two 380mm x 760mm strong bands at each end with following loading. S.No. Loading Axial force Moment Shear 1 DL+LL 1950 600 20 2 Seismic load 250 4800 700
what is parametre for M25 after 7 days strength
What is modular elasticity?
how to tie 10 legged stirrups