How much depth of excavation have to do for Highrised builldings?if Raft foundation how much,and Pile foundation how much?
Answer Posted / kabir
for raft foundation depth of exacavation is nearly about
3.0m . because due to having the raft foundaton their will be provision of basement in that structre ..........
| Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
Kindly post me previous year interview questions with answer for post of DY. Manager (civil engg.) for GAIL, NTPC, IOC, OIL and ONGC etc.
Technical Question of Civil Engineering
In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting? 2nd :- I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?
Sir, Iam Applied in rrb for the posts of Junior Engineer.I want to know about the or question previews to study well.Pl send it to shukla_varun1985@yahoo.com.
can i get civil engineering test papers.......?????
how can we calculate steel value, depending on load
5. Two long boundary walls run parallel to each other at a center to center distance of 1 meter apart. The width and height of the first wall are 0.30 m and 2.5m respectively. While those of the second are respectively 0.18m and 3.5m. Plot the distribution of vertical stress intensity due to walls on a horizontal plane, 1m below ground level. The walls have negligible depth of foundation and are made of brick masonry (y = 19.2 kN/m cu)
Suggest how many column, beem, etc required for 30 mtrs x 21 mtrs width x 8mtrs height for industrial shed of ground floor. I want to know the quantity of tmt steel consumption and Concrete consumption for budgeting
sir I got selected in rail vikas nigam limited and they call for interview but i don't what they will ask in interview please guide me if you have any experience
manhole chamber having height of 2300 mm and thickness of brickwork is 230 mm and dia of opening covering is 560 mm and bottom length vertical is 1500 mm (1:4) brick masonry and plaster 12 mm on both sides..how to estimate the no bricks used with mortar cement bags and sand for total chamber including plaster.
kindly mail me by attaching files , formats for quality checks of common building materials like cement , concrete , bricks , sand and aggregates plz send my email id- VMANDAL91@gmail.com
400 ku d/c clearess ketan hota hai?
please send latest placement papers of hpcl officers trainee test. i will be very thankful to you.
Draw a neat sketch showing the 'throat' of a welding in a plate girder ?
What is the per cu. mt. price of ready mix in Gujarat region.?