adspace
What is the exact meaning for under & over reinforced beams
& when they have to used..
Answer Posted / dinusha samarasinghe
reinforced concrete beam section in which the failure stain in concrete is reached earlier than tha yeild stain of steel is reached are called over r/f section
R/F concrete section which the steel reaches yeild stain at loads lower than the loads at which the concret reaches failure strain mean by under R/F section
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
hii.plz send me hpcl placement papers for officers trainees for graduate engg plz my email id is ajm_knit@yahoo.com
Suggest how many column, beem, etc required for 30 mtrs x 21 mtrs width x 8mtrs height for industrial shed of ground floor. I want to know the quantity of tmt steel consumption and Concrete consumption for budgeting
Please tell me Detail cost of providing& laying nominal mix design 1:2.5:5,40mm nominal size.curing complete e/c cost of form work in foundation and plinth i/c carriage.
pls send me interview question paper with answer of EIL/AAI/UPSC/RPSC because i am doing prepration of compitation exam of UPSC for the Asst. Executive Engineer
water leak detection system question & answer
sir I got selected in rail vikas nigam limited and they call for interview but i don't what they will ask in interview please guide me if you have any experience
Technical Question of Civil Engineering
Re: Can anybody help me by attaching files , formats for quality checks of common building materials like cement , concrete , bricks , sand and aggregates? please my email id is smgujjal@gmail.com
What is Density of cement, sand & aggregate ?
Anyone have sample questions for bhel interview.please send me as Iam appearing for the interview on 19th sep2008. Kindly send this to my e-mail: arun_prasath_n@yahoo.co.in
can i get civil engineering test papers.......?????
cud any one send me tech quest paper(civil engg) at tarizus@yahoo.com
what is the difference between replacement of cement by groundnut shell ash
In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting? 2nd :- I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?
What is the strength of 1:6:12 mix?