my scenario is repetitive manufacturing (REM) make-to-stock
(MTS)production for sugar industry. What are the things, I
have to customize for this scenario, to the PP point of
view..
Answer Posted / shamshuddin
Repetitive manufacturing is selected in MRP4 TAB
one is check box repetitive , REM profile , production
version (Each pcc create one PV).
month end process
1) std cost ck11n
2) mark and release ck24 other wise run Ck40n
cost center level
assessment and distribution
actual activity price calculation
revaluation of activities
actual OH calculation
wip
variance
settlement
| Is This Answer Correct ? | 1 Yes | 1 No |
Post New Answer View All Answers
What are the types of master views for production and planning?
• How are basic order dates determined?
Explain PI sheet.
What is MRP Profile and MRP Group?
You want to insert an inspection check point at the end of an operation. How would you do that?
What is golive actually? What is the role of a functional consultant in golive actually?
Are there any reports in sap to list of material requirement from ltp ?
list the important tables used in pp.
What are the parameters are there in Order type or in dependent para. config?
How do I find which is the recurrent item in a production order? In the missing material analisys I got message MF 331, but the BOM or the production order don'thave any recurrent item Thanks
Difference between PP and PI.
We defined sop in months. However, during sop transfer to demand management, our independent requirements are appearing in weeks. How can we correct this from weeks into months?
What is the planning horizon?
Explain what is the need of mrp list if the stock requirement list is already given?
Can we create production order without bom and routing ?