how much quantity of cement and sand required for
construction of 10 cum brick work( Brick size
3"*4"*9"(Standard size ) an d for 10 cum construction of SSM
(Size stone masonary) with Cm 1:6 for both.

Answer Posted / bhupendra potpose

Consumption & Rate analysis Brick Masnory 230mm 1:6
Superstructure With scaffolding

Providing and placing brick work 230mm 1:6 Superstructure
With scaffolding
1.3Ref: use 1..3 standard
Proportion of materials
Cement 1
Sand 6
Total 7
Std constant(1.5) / Total of proporttion(4)
0.186
1) Required volume of cement for 1 cum.

1 Proportion of cement 0.19
Add wastage(2.50%) 0.005
Vol of cement for 1 cum 0.190
0.035 is cum of per 50kg of bags 5.44.

As per standard we assumed that in 1cum of brick work ,the
quantity of mortor (Cement & Sand )is consider in
quantity. (24%) 1.28
Cost of cement per bags 325
Total cost of 1.34 bags 415.39

2) Required volume of Sand for 1 cum

2 Proportionof Sand 1.114
Add wastage(2.50%) 0.028
Vol of Sand for 1 cum 1.142
As per standard we assumed that in 1cum of brick work ,
the quantity of mortor (Cement & Sand )is consider in
quantity.(24%) 0.268
Cost of sand per brass 875
Total cost of 0.284 cum sand 234.85


3)Required brick for 1 cum of size 230x115x75mm

Actual Vol of one bricks is 0.00198cum,&
10 gap Allaround is become 0.00255
Nos of bricks in 1cum0.00255 1 392.16
Add wastage(10.00%) 39.22
Total Required brick for
1 cum 431.37
Cost of bricks 5.00
Total cost of brick 2156.86

A)Total material cost (1+2+3)
2807.10

4)Cost for Manpower ,Mixing ,Shifting ,
placing etc, Rs 15 / sft-Mumbai, 529.80

5) Cost for screeing,
cleaning ,of sand (10%) 333.69
6) Cost for Tools ,
Safety, curing etc(5%) 183.53
B) Cost of labour on
total material cost (4+5+6)
1047.02

C) Cost of Material & labour (A+B) 3854.12

5)Add over head(5%) 192.71
6)Add profit on(15%) 607.02


D- Total of (C+5+6),Over head & profit cost
P/A P230mm,1:6 Per Sqm. 4653.85
If the brick work is required to .


convert into Sqmt
1) for 230mm ; 0.23 1070.39
2) for 115mm ; 0.115 535.19

Is This Answer Correct ?    11 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is progress payment?

704


how to find out hard strata in bored pile when the DMC method adopted.

5310


what will be the total emoluments for deputy surveyor in APPSC in the payband of ( 9460-27600). please give me the detailed information step wise?

1872


in one hour , one 200 excavator , how much quantity (mcube)can load ? soil is not hard not soft

1495


Design a built-up column carrying an axial load of 1200 KN. Its length is 8m and it is effectively held in position at both ends and restrained against rotation at one end. Assume yield stress of 250 mpa

1746






What is the largest concrete dam in the world?

683


how to identify the failure of building by expansive soils

1224


Define What glue is least sticky?

642


A super elevation of 60 cm has been provided on a 8m wide road and a curve of 260m radius .calculate the max.speed in km/hr of the vehicle that can be negotiated safely? Plz answer with full solution.thanx

1347


How to calculate concrete in percentage wise ,for example cement 18% sand 40% aggregate 40% and Stell 2% ,I need and??

1588


The largest size of paper used in plotter to print the drawing made by Autocad .

1294


what is the mode of method of face bar measurement

2054


What is a bearing capacity of soil?

805


What is the primary difference between adsorption and absorption?

724


Define What is an ice dam sock?

689