how much quantity of cement and sand required for
construction of 10 cum brick work( Brick size
3"*4"*9"(Standard size ) an d for 10 cum construction of SSM
(Size stone masonary) with Cm 1:6 for both.
Answer Posted / arvind vyas
The size of brick be 230mm x 115mm x 75mm
Vol.of brick( w/o mortar) = 0.00198 cum.
Thk.of mortar be 12mm.
vol.of brick with mortar = 242mm x 127mm x 87mm = 0.00267
cum.
No.of bricks in 1 cum. with mortar = 1/0.00267 = 373.99
Say = 374 bricks.
Cement Mortar required = 1-(374 x 0.00198) cum= 0.259 cum.
Say 0.26 cum
Add 15% for frog filling and wastage while execution.
Vol. of wet mortar = 0.299 cum.
Vol. of dry mortar (increase by 30%) = 0.388 cum.
For CM of 1:6
Qty. of cement = 1/7 x (1440 x 0.388) = 0.055 cum.
Qty. of sand = 0.055 x 6 = 0.330 cum
| Is This Answer Correct ? | 8 Yes | 4 No |
Post New Answer View All Answers
please give the detail design for the soring and shuttering for 8.5m deep excavation in the sandy soil for 25x10 rectangular streaches
Process of pcc in wateredug
is it fair to recruit another prestressing agency once earlier agency has provided guide cone for post stressing the Concrete -I girders? It is observed that the bearing plate of another agency is not matching with the earlier one resulting in protruded strands after stressing from the face of girder. Kindly advice.
what will be price of 1:2:4pcc per kg?
What goals do you have in your career?
Bernaullis theorem deals with the law of conservation of mass momentum energy none
what is the cost difference of a same structure when it is constructed with brick masonary and when it is constructed with block masonary and concrete as a frame structure????????????????????????
What are the different approaches in designing the floors of the service reservoirs?
In case if concrete box girder bridges how is the number of cells determined?
what is features of a typ-ical modern air-conditioning installation?
how much need sand and cement for 1 cft roof construction?
How many cum of 9.5mm stone in 1 ton ?
what is the minimum cement content for M20 & M25 as per is code -456(2000).
What is labor and material payment bond?
what is E