If the scenario is''Party is supplying some material we
have to do the some processing operation on it, how it cab
be handled in SAP"
Answer Posted / ajit kumar santi
You have to use Sub-contracting in MRP-2. proc type-F and Special proc type-subcontracting
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
What happens to plan after it has been converted into production order?
What is purpose of schedule margin key?
What is meant by payscale structure? How did you configure the payscale structure?
How can I use variable size items?
What is golive actually? What is the role of a functional consultant in golive actually?
What is the purpose of Catalog? how you reverse UD?
Standard mrp steps
Can mrp be carried out for one particular level of a bom ( level code : 0001/0002 etc)?
suppose we have sales order-40, PIR-25,warehouse stock-40, so when we run mrp,what quantity the system displays with MTO & MTS. How?
Explain what happens to planned after it has been converted into production order?
What do you mean by pooled capacity?
Checkdigit example
What is sap pp?
Are there any reports in sap to list of material requirement from ltp ?
What is the use of mrp group?