In a thermal power plant ID Fans running with full load but
boiler load is only 80 % give reason ?
Answer Posted / a k handa
Coal feeding may not be as per the required load.
| Is This Answer Correct ? | 7 Yes | 8 No |
Post New Answer View All Answers
what is the trip circuit supervision in an electrical meaning?
what is restricted earth fault explain in details
what does mean by kva rating
im try to calculating seawater flow required for SW-FGD system. I need a guide, equation or method to do it, can some one help me! Thanks very much
What is difference between secondary Air & Tertiary Air and Their use.?
How to calculate boiler capacity? I have 1 Autoclave, Which has to use for AAC block. Dimension for this Autoclave is - 13 Meter Length & 2.2 Meter Diameter.
What is LB-SR.
some one can tell me how residual type excitation is provided through transformers to an AC generator without any battery or PMG&excitor
How to calculate power press toneage
can u please tell me how to calculate the concrete quantity for a under reamed pile? r=300mm,depth=3m for a cylinder and for bulb l=.750mm,width=.525
How do you consider that you can improve and what assistance do you need to achieve this
DCS marshaling Cabinet Power supply can be replace during plant running time? Answer Yes it is possible. I am talking about the controller and cards power supply modules. They are always redundant and connected through diode so that if one power supply fails the other can take the charge immediately.so it is possible to replace one of them in running plant if the other one is healthy. MY question is how switching done.
Which will have more strain energy 1.Spring 2.Circular disc 3.Solid square plate.
Qatar Fertiliser Company (QAFCO) Shortlisted me for interview (got the intel from my source) for Field Operator- Utilities post. Please let me know what kind of questions they asked? ... this position requires 5 years of experience in Power Plant and background Diploma in Electrical/ Mech. ... my Background is Electrical and I am a sub Assistant Engineer (Operation) at a private HFO based Power plant... PS: Please Let me know what preparation should I take to obtain the Interview which will be take place In Bangladesh soon
how to differentiate between "ALL fuel lost" and "All Fuel Lost" in Boiler MFT condition?