We have .ht motor which is 60Hz.we run on 50Hz.so that it's speed reduce
but we had one prob.that motor winding temp increase up to 135 deg.we
want reduce this temp.what to do?we arrange ext.cooling fan but not much
effect.we want reduce this temp. Inhouse without affecting much.cost. also
don't want reWINDING OF MOTOR?
Answer Posted / k.prakashchandra
As you have reduced the speed ,the cooling effect of the
shaft mounted cooling fan is also reduced .Either you have
to reduce the load by about 10% or replace cooling fan .
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
It is desired to flood light the front of a building 42 meters wide and 16 meters hig.Projectors of 30 degree beam spread and 1000 watt lamps giving 20 lumen/watt are availabl.If the desired level of illumination is 75 lumen/m and show a suitable scheme.Assume the cofficient of utilization, deprecitation factor and waste light factor are 0.4, 13 and 1.2 respectively.
What type of wiring series or parallel is used for conventional and addressable type FAS & why?
What is minimum permicible value of leackage current for LT Panle when applying voltage up to 3 KV for 5 Minuits?
WHATIS TIME CONSTANT? WHATIS ITS SIGNIFICANCE? ILLUSTRATE THROUGH EXAMLES.
Why temperature rise is conducted in bus bars and isolators?
Dyn1 transformer vector group testing how to do
A commercial Building is designed with 14th floor levels with indoor substation of three phase transformer with rated capacity of 1000 Kva.The transformer delivered 65% of its rated capacity at 0.67 power factor lagging.Because of low power factor, the power customer was penalized and certain cost was charged accordingly based on every point percentage lower than 85%.This situation may repeatedly happen on the succeding energy bills of power customer.The power customer is desired to improve its historical power factor of 0.67 lagging and no further penalty be impose by the local power company on the next bill. Q: Identify the appropriate solution you want to offer to Client?.Justify SCIENTIFICALLY and MATHEMATICALLY the principles behind the solution.
how can maintain the power factor and why and this is how do work tell us
What is Phase margin?
In Generator How suction compression power and exhaust works ?
What is the approximate value of stacking factor?
What is lc oscillator?
Please send 110 kv sb station full single line drawing(sld)
What is the importance of counter based plan & how is it scheduled?
An ELHNC 80amp 240v 30mA RCD is tripping periodically, every 30 - 180 seconds is it safe to disconnect the protection circuit?