Answer Posted / kiran kumar kakolu
Maintaining Versions
Call up the transaction as follows: Menu Path
Tools ® AcceleratedSAP ® Customizing ® Edit Project
Transactioncode
SPRO
Choose SAP Reference IMG.
Choose Controlling ® General Controlling ® Organization.
Choose for Maintain Versions.
Select Version 10 and doubleclick on Settings by fiscal
year.
If the Determine Work Area: Entry dialog box appears, enter
1000 or 2000, then choose .
Select the line for fiscal year 2000, then choose .
You can now see the current settings for planning year 2000
in version 10. This version includes, for example,
integrated planning and the possibility of copying
versions. Currency translation occurs at the average rate
with a value date of 01.01.1997. To display more
information about the remaining fields, position your
cursor on the relevant field and choose F1 help.
You now process the versions required for fiscal year 2001,
using the settings from 2000.
Choose .
Choose New Entries.
Enter the following data: Field
Version 10
Version 20
Version 21
Fiscal year
2001
2001
2001
Integrated planning
Select
Deselect
Deselect
Copying allowed
Select
Select
Select
Exchange rate type
M
M
M
Value date
01.01.1997
01.01.1997
01.01.1996
Integrated planning Cost centers/bus. processes
Select
Select
Select
Valuation version for IAA
0
0
0
Choose .
If the Prompt for Customizing Request dialog box appears,
choose . Enter a description, then choose . Choose .
Choose .
You can see that planning year 2001 has been added to the
list.
Choose .
Repeat this procedure for versions 20, 21 and 110.
Choose until the overview tree appears.
| Is This Answer Correct ? | 0 Yes | 1 No |
Post New Answer View All Answers
Explain posting of costs to cost centers? : co- cost center accounting
How do you assign a fiscal year variant to a company code?
Hi, Need a interview question and answer for different company's please revert me soon Yash
Define the relationship between controlling area and company code?
How do you maintain the number range in production environment?
What is done by gr/ir regrouping program?
How capital wip (work in process) and assets accounted for in sap?
What are the application areas that use validation and substitutions?
How do you configure the assignment of variances from product costing to copa module? : co-pa
How do you set up depreciation area postings to fi from fi-aa? : fi- asset accounting
What are correspondence types in ar / ap?
What are the different types of cost elements? : cost center accounting
What is the global company code currency?
What is the land scape in sap?
Can we change price control from S to V in mid of the year, If we can change what is the process steps we will follow from CO end?