what should be the strength of Concrete cube strength for 7
days, if the designed mix is M20?
Answer Posted / g.mugesh
Grade of concrete:m20
7days test (67.5%) - 20*67.5/100=13.35 N/MM2
28days test(100%) - 20 N/MM2
Is This Answer Correct ? | 19 Yes | 10 No |
Post New Answer View All Answers
PL.tell me about civil engineering questions with answer
What applicable rate of wct in bihar
what is the soil bearing capacity for a 5 floor multistorey residential building and which type of soil ? what is plinth beam? in wall load calculation center to center column distance is considered or not/
How many square meter can mason layout chb per hour
why do we not deduct volume of steel to find actual volume of concrete in practical???
Hi all, please guide me about the volume. And percentage. Of steel fibre to be used. My project. Is Sifcon.
I measured pcc work as 15.34 m cube , the ratio is 1:5:10 ,want to know the cement, sand and metal used for pcc measured as 15.34 m cube at this ratio.
What is the l/d ratio of cantilever beam?
For making a new road in a village having a school & hospital , tell the steps of construction systemically ?
1)What is the total volume of aggregates required for 1cu.mtr.solid hard concrete? 2)What is total mass of wet concrte and dry concrete after 28 days of M25? 3) Is 28 days strength is the final strength of concrete or it gets increasing as the time period increses.? 4)What is the volumetric proportion of concrete grade of M25.M30,M35,M40
how to calclate the SHUTTERING TAKEN CONCRETE LOAD? WHAT IS THE LOAD BEARING CAPACITY IN STEEL SHUTTERING PLATE? WHAT IS THE CONCRETE LOAD IN (MASS) IN THE SHUTTERING PLATE. PLATE SIZE IS 120CM* 90CM CONCRETE WALL LENGTH IS 10M ,WIDE IS 60CM, HEIGHT IS 1.2M PLS TO SENT THE CALCULATION.
how to find hardness of water?why it should be determined?
sir, please send me the web address of chennai railway to know the online examresults of junior engineer[civil].
What is the tensile strength of marble?
What is the cost of formwork for columns/beams/rcc walls also what is the cost of shuttering for roof slab at height of 25 feet