What is Hi-Pot Test for Grid Station HV Equipments?
Answer Posted / shao
Thank you so much Naresh!
But i think we only measure the respective leakage current at that phase on which we have applied voltage.?
e-g; Applied 40KV at Red phase for 60sec, & measured leakage current was 0.6micro Amperes.
Actually im seeing this testing at a 132KV Grid Station.
| Is This Answer Correct ? | 4 Yes | 0 No |
Post New Answer View All Answers
Load break swicth maintenance procedure.
What is the voltage gain or transfer function of amplifier?
HOW WE CHOOSE EARTH'S POTENTIAL AS ZERO V?
According to underground cables a) stress b/w sheath & conductor is high b) inrush of core & conductor
how can i reduce sparking without stepdowning the voltage
Can 4pole (3 phase+neautral )RCCB proper functioning in only 3 phase load (no neautral, no Earth) ?
HOW TO CALCULATE EARTHING SIZING?
Can i use the B-curve MCB instead of C-curve MCB
What are the components of feedback control system?
How to test the vector group of a Yd11 transformer? what are the relations to be checked between various vectors to confirm this vector group?
how we can adjust for three phase motor cold stall time ,hot stall time and thermal register set up?
how 650 volts creates? where is use?
what is RNG in the DG synchronizing by PLC?
Why efficiency of generator is higher than motor at a particular load?
our factory is going under construction mean time transformer 1000 kva 2 nos &load break swithch 12 kv & 4 nos 750 kva 2 nos & 380 kva 2 nos generator to be errcted.how to arrange earth pits &how to earth connect & neutral pit how to calculate in earth bit size.