Bitumen grades are 30-40,60-70, 80-100. what is mean by 30-
40
Answer Posted / abir kumar ghosh
30-40 means bitumen having penetration of a needle between
30-40 mm with standar weight on it at 25 deg Centigrade.
Lower the penetration is higher the viscosity.
The test is done with the apratus called Vicats apparatus.
Is This Answer Correct ? | 28 Yes | 25 No |
Post New Answer View All Answers
I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?
What is the requirement for over all CG of DG from the foundation surface to absorb the vibration of heavy set.
How can you distinguish between sorption, absorption and adsorption?
where can i get the previous question papers for rrb section enginerr (civil)
How we can calculate the cement, sand,bricks , water , quintity in 1:6 Ratio 1 cubic metre b/w and 1:4 Ratio in 1 Squre metre b/w????
How many types of slabs are there & how to design it?
how many men days of loburs and masons are requirete for 1 cum,pcc (1:2:4),Pcc(1:3:6) and Pcc(1:4:8) thanking you
Suppose a new brick wall is being constructed,and the courses and not aligned horizontally,what negetives can it cause?
What is the Roll of Water Bonding under VDF road?
100mm block work 64 bags of cement used 150mm block work 286 bags of cement used 200mm block work 20 bags of cement used patly work (M15) 293 bags of cement used mortar ratio is 1:5 how to calculate volume of sand in cum & no. of bags
what isload waring calculation
what is spacing of wallar support of 3m column. the thickness of column is 0.25 m.
What is Density of cement, sand & aggregate ?
1. What is coefficient use for calculation of shuttering. 2. What is coefficient use for calculation of reinforcement in one cum of concrete.
How to calculate the force on a column of three story building. What should be the base concrete height?.