how much quantity of cement and sand required for
construction of 10 cum brick work( Brick size
3"*4"*9"(Standard size ) an d for 10 cum construction of SSM
(Size stone masonary) with Cm 1:6 for both.

Answer Posted / jocky

mortar required for 10 cu.m brick work

Dry mortar = 30% of brick work = 3 cu.m

one part of cement=3cu.m/sum of proportion

(3/1+6)=0.428cu.m

cement required in bags...0.428/vol. of one bag of cement

(0.428/0.035) =12.23 bags ..take 13 bags of cement

sand = 0.428*6= 2.57 cu.m

Is This Answer Correct ?    24 Yes 10 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

the volume of cement req for 70cum of brickwork in 1:6 cement mortar is approx is equal to 3cum 5cum 7cum 1ocum

1621


Pile height is 4.3m. 2nos. under reammer. bulb nose is 75mm and height is 400mm. pile dia is 375mm and overall dia 940mm.pls. help to calculate concrete in pile and bulbs separately. What is formula for bulb volume calculation ?

1272


how much need sand and cement for 1 cft roof construction?

3965


How to determine thee cut length for steel reinforcement bars in R.C.C design

1055


suppose we have a tendency to make a hole on the surface of the simple supported beam, than where we goes to make it?

1661






Explain major difference between auto level and dumpy level?

739


use ofr concrete as per grade ?

1631


all technical question

1672


what is the difference between np2 and np3 concrete mix

1549


in 2 way slab can additional compressive reinforcement can be provided if yes than in which conditions it is required ?

1797


What is the strength of 1:6:12 mix?

2589


what pressure the NP2 class RCC pipe can sustain?

2206


how to frame the sentence in voucher pad ? Description : 1.Food Expenses during site visit 2.Stamp Paper approval expenses 3.Travelling expenses 4. sweet distribution

1682


How to hide dimensions in autocad?

632


How to do bbs in excel format

1587