when you enter a po with item quantity 10 price RS.100/-.The
vendor sends an invoice with 15 quantity. NO GR.In real time
what you have done are you post the invoice.explain
Answer Posted / rajesh
If we required the additional 5 nos we can do GRN by giving
tolarence level to the material and post the GRN.
If tolerance level is not possiable take indent for another
5 Nos and amend the PO with 15 Nos and release it and then
do GRN for 15 Nos.
If we dont want the 5 Nos post the grn for 10 nos and send
back the 5 nos to vendor by raising the debit note against
the invoice.
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
A stock transfer was done between two plants belonging to same company code and between two plants belonging to different company code. What will be the difference between the two?
How you can link a document to a vendor master record?
The material does not have a master record. How can we procure that?
What is batch information cockpit?
What happens when a goods receipt is posted?
Explain the importance of the batch record?
How to create pr or po by mrp?
How are components consumed in case of subcontracting?
What are the different ways of organizing purchasing organizations?
What is the subcontracting cycle?
How is the information of material master records updated?
List the steps involved in automatic account assignment configuration.
Mention what are the types of special stock available?
How do you generate an automatic po after creating a pr using a particular material?
If the recruiter is expecting thorough Knowledge\exp on the following topics:- o Material master o Vendor master o Purchasing o Release strategy o Inventory management What type of questions can i expect ? Please mention some important questions