what is the silt(for sand) allowed persentage as per IS
CODE
B/W:
PLASTER:
CONCRETE :
Answer Posted / mahendra mohan srivastava, acc
we have two type of silt test 1 is by volume and 2 is by
weight,
by volume in 10 min it should be 20-40%, after 3 hour 7-8%.
by weight not more then 8%.
| Is This Answer Correct ? | 9 Yes | 4 No |
Post New Answer View All Answers
How to do base isolation for RC framed structure using ETABS software?
how to calculate testing date
strength vs shape factor
How to make tiles floor step by step procedure?
what is the composition of good brick ?
How much of the strength of concrete comes from post- production curing?
Gidc technical que paper
How to design 12*12*14 room having rrc slab ,coloum, beam,foundation?
I want some common questions which have been asked in interviews of NTPC Limited,Satluj Jal Vidyut Nigam Ltd.,and Bharat Heavy Electricals Ltd.
for 32 dia (EQR HYSD steel) bar how much deduction for 45 and 90 degree band
what is the water cement ratio? how to calculate it? list the wt. of constructions materials including concrete both ordinary and light wt. concrete
For submitting the project loan for bank Residential bldg,Suppose we take Provinding RCC mix 1:2:4 for footings No of footings,length ,Breadth,Height ,qty in cum, at last unit/Rate(Rs) ,i would like to know how do we get the unit/Rate
How many lbs are there in a yard?
What is Architect-Prepared Contract?
what is the Purpose of Adding 20% of wet mortar & 1/3rd to Dry Mortar for PCC & Plastering & Rcc .is there any standard method for adding this .?