DG B-check,C-Check,D-check is depending upon the running
hrs.If the running hrs is not reached as mentioned.How to
conduct the DG checks.
Answer Posted / sharath patel
if the running hours not reached means we can conduct the
checks by the number of days from the comissioning date.
| Is This Answer Correct ? | 7 Yes | 9 No |
Post New Answer View All Answers
how to copy from plc ge fanuc versamax series,all input and output, adress, and printout.
How to findout raw or ups power? its not indicated in socket,
Define demand factor?
In convertor can we use rectifier thyristor in place of invertor thyristor with explain.
what are the main faults that occur in stabilizers? How they corrected and resolved ? Types of stabilizers ?
can a 150 kva 3 phase 440v/230V delta-wye step down transformer can be use as step up transfoermer with connected loads at 440v side?
Control wiring of a dol starter for forward and backward
what is the circutor?why we use it ?
I WANT YHE TECHNICAL AND ELECTRICAL SPECIFICATIONS OF 2x4MW 11KV 2x10MW 11KV 2x25MW 11KV 2x100MW 11KV HYDEL POWER PLANT i.e PROTECTION SYSTEM,MONITORING,CONTROL SYSTEM,GENERATION,SYNCHRONISATION,METERING PLEASE SEND THE DETAILS TO MY MAIL ID SPRAVEEN_222@YAHOO.CO.IN
What will be the effect if I use inverter as UPS mood?
Differentiate between Zero and Negative sequence current
difference between high and low impedance BUS BAR relay??
234 MVA Generator 3 phase Short circuit current Values required? Gen set Rating-234 MVA, Gen Voltage-18kv, PF;0.8, Xdv:23.5 %, Transformer Rating-18/380KV, 680MVA,Yndd1 two winding, Step up TR, ZT:35.50 %,X/R 4.33 Gen CB Position, CB open ,Disconnected open, Generator Running Voltage 18 Kv, Bi mistakes generator side earth switch Closed during that time short circuit current level in 3 Phase required, and how to test on site 234MVA Generator Short circuit current,
Single line diagram for dbb (double bus bar)system.
what is the maintaining Cf in UPS.