Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

customer ordered quantity 50 for material A but avaialable
stock is 20 if the company decided to get the remainig
stock from an external vendor i.e 30 in third party process
how to complete this order pls explain in detail how
purchase requisition, purcchase order is created in this
senario,how are schedule lines carried out? how is total
ordered quantity delivered to the customer? how is billing
done in this process??

Answer Posted / subha

We can do this in any of the fallowing ways
. 1 We go in for part delvries where we deliver 20 goods
and for the other 30 we go in for third party and raise
the PR in schdule lines and the automatic PO GENERATION in
ITEM CATEGORY AND excute the order . We do individual
delveries in this case and biling is also done seperately

CASE 2 :
We check if any other plant or subsidariy of ours are
capable of realseing the required material if so we can go
in for sto process

Case 3:
We raise the order for 30 a goods to the vendor and ask him
to deliver at a comman palce ( lean ware house ) of the
company and we also send the goods to that stock point .
combine the order then do a single delivery and do a single
billing

Cas4 :
In this we check the possibilites in respect to cost ;
technical know how and the time to produce this order but
it is a very very rare case

Case 5 :
We can go in for subsition process for the 30 again this
is not an easy process and dpends on the customer

In either way the frist 3 options are commanly put into
praticse

Is This Answer Correct ?    12 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

why tolerance groups are to be define in sap?

1201


How to disable the 'import all' button on stms for the queues in sap? : transportation management

1430


what is the difference between sd account key and fi account key?what si a variant and its use?

2518


Can you combine orders into one invoice?

1216


How do you maintain fiscal year variant?

1165


What sap systems have integration capabilities with sap transportation management? : transportation management

1176


What does a/c group control customer?

1103


In back order process system follows backward scheduling or forward scheduling? please give ur valuable answers

917


Is it possible to create sales order for 40 items if the quotation is sent for 30 items?

1294


Hi Team, this question is related to 3rd party. customer is given order for 20 materials and vendor delivered to customer only 10 material . As per my knowledge vendor invoice will be for 10 material and customer invoice will be for 10 material but my question is how billing quantity will change in sales order against which we have need to create customer invoice for 10 material only. what configuration we need to do for update sales order quantity for order related billing for customer. how vendor will deliver rest 10 material to close this order? could you please share your input with screen shot. Thanks in Advance.

1932


Explain credit management.

1161


Which block stops the system from creating the picking list?

1226


Would you have different customer numbers if your customer was serviced by more than one company code?

1117


accounting document is not getting generated for sto process. where is the control for this ? Thanks in advance

1833


Give examples for standard output types in sd.

1107