What should be the 28 days cube strength for M-25 grade
concrete?How it is connected with acceptance criteria of
fck+3 as per IS 456-2000 and why?
Answer Posted / viki
the 28 days cube strength for M-25 grade
concrete should be 25N/mm2.
acceptance criteria are some conditions defined by IS 456
regarding characteristic strength of concrete when the mix
is prepared on site.strength tests are performed on 4
blocks of concrete.avg strength is calculated.
then fck+3 means that the avg strength of the concrete mix
at the site should be 3N/mm2 greater than fck of mix.
i.e. mean strength= (fck+3)N/mm2
(refer IS456 CLAUSE 16)
| Is This Answer Correct ? | 18 Yes | 7 No |
Post New Answer View All Answers
Explain what is zoning permit?
How are freeway bridges built?
how much brick, cement, and sand required in 1mtr X 0.23mtr X 1mtr brickwork(1:4), 230mm thick wall and 10mm thick mortar , brick size 230mm X 70mm X 110mm
Which code specifies the specification ofthe construction joints to be provided in the raft slab of a basement which is 6 m deep.what should bethe detail of such a joint?
what is escalation?how it is done?
4. Differentiate between NC and OC soils. Draw curves for (i) Stress vs Strain (ii) Volume charge vs Strain (iii) Pore pressure vs Strain for these soils
which are the Indian auther books for STONE COLUMN/GRANULAR PILES?
Describe the various methods of concrete curing?
A 16 pile group, consisting of diameter concrete piles, were cast in situ in a clayey soil whose unconfined compressive strength is 1100 psf. Each pile is 60 ft long and the pile spacing is 2.5 times the pile diameter.The water table is at the ground surface and saturated unit weight of the clay is 118 lb/cu.ft. using a factor of safety 3 and a reduction factor =0.45, compute the allowable capacity of the piles acting as individuals
How many pyramid in egypt?
1) write Short notes about Shellow & Deep well? 2) What is the full form of SPT & SMB? write short notes. 3) write short notes about efficiency of Riveted joint.
why we are using stub column..? is it possible to construct steel stub column..?
is there any codal provision for soil cousion over the Hume pipe of Dia 1.2 m.
How do you prepare Material Recovery Statement for deduction from contractors bills?
Labor requirement for each item needed? Lean Concrete 103.550m3 Concrete for Foundation and Structure 1753.000m3 Expansion joint 288.000m Contraction joint 127.000m Dowel bar 450.000m