what should be the strength of Concrete cube strength for 7
days, if the designed mix is M20?

Answer Posted / viki

generally concrete attains 60-70% of its 28 days strength
in 7 days.After 28 days strength of M20 concrete will be
20N/mm2.so after 7days it would be 12-14 N/mm2.

Is This Answer Correct ?    113 Yes 28 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

plz.show development and anchorage length in simple diagram.

2637


VAT and CST ? Which benefits for buyer ? Why benefits?

1902


can i get civil engineering test papers.......?????

2550


please send me bhel questions on rupesh.017@rediffmail.com

2797


HOw much % of premium on DSR-2013 currently

2048


Suggest how many column, beem, etc required for 30 mtrs x 21 mtrs width x 8mtrs height for industrial shed of ground floor. I want to know the quantity of tmt steel consumption and Concrete consumption for budgeting

1896


PLS.......... ANY ONE CAN FORWARD ME PREVIOUS QUESTION PAPER hpcl civil engg

2422


pls send me interview question paper with answer of EIL/AAI/UPSC/RPSC because i am doing prepration of compitation exam of UPSC for the Asst. Executive Engineer

3236


please send latest placement papers of hpcl officers trainee test. i will be very thankful to you.

2397


How much area, in square meters, will one liter of paint cover if it is brushed out to uniform thickness of 100 microns?

1618


what is the difference between replacement of cement by groundnut shell ash

3306


kindly mail me by attaching files , formats for quality checks of common building materials like cement , concrete , bricks , sand and aggregates plz send my email id- VMANDAL91@gmail.com

1921


Technical Question of Civil Engineering

2358


5. Two long boundary walls run parallel to each other at a center to center distance of 1 meter apart. The width and height of the first wall are 0.30 m and 2.5m respectively. While those of the second are respectively 0.18m and 3.5m. Plot the distribution of vertical stress intensity due to walls on a horizontal plane, 1m below ground level. The walls have negligible depth of foundation and are made of brick masonry (y = 19.2 kN/m cu)

2211


In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting? 2nd :- I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?

2233