Brainstorming and the Delphi technique are two types of information-gathering techniques found in which process? A. Risk Management Planning B. Risk Response Control C. Risk Identification D. Quantitative Risk Analysis
What do you think you can bring to this position?
Performance reporting tools and techniques include all of the following except: A. Earned value analysis B. Statistical sampling C. Variance analysis D. Performance reviews
If you know expected value is 500 and the standard deviation is 12, you can say with approximately a 95 percent confidence rating which of the following? A. The activity will take between 488 and 512 days. B. The activity will take between 464 and 536 days. C. The activity will take between 494 and 506 days. D. The activity will take between 476 and 524 days.
What is the name of the unplanned response used to deal with negative risk events in the Risk Monitoring and Control process? A. Mitigation B. Contingency plans C. Workarounds D. Corrective action
How will prioritize tasks in your projects?
Your company has asked you to be the project manager for the product introduction of their new DeskTop Rock media system. You recently published a document that establishes the scope baseline. Which of the following is true? A. This is the scope statement, which is an output of the Scope Planning process. B. This is the scope statement, which is an output of the Scope Definition process. C. This is the scope statement, which is a tool and technique of the Scope Definition process. D. This is the scope management plan, which is an output of the Scope Definition process.
Your project was just completed. Due to some unfortunate circumstances, the project was delayed causing cost overruns at the end of the project. This information might be useful on future projects in all of the following activities except: A. Cost estimating B. Allocating resources C. Product verification D. Activity estimating
You are going to lake some performance measurements for your current project. You know that PV = 450, AC = 500, and EV= 375. What is the CPI and SPI respectively? A. CPI = .90, and SPI = 1.2. B. CPI = .75, and SPI = .83. C. CPI = 1.2, and SPI = .90. D. CPI = .83, and SPI = .75.
You are a project manager working on contract. You’ve performed earned value analysis and discovered that the project will be completed on time and under the original estimated amount. This means the profit to your company will decrease as will your personal bonus. Which of the following should you do? A. Add activities to the project to increase the cost enough to meet the original estimated amount. B. Tell the customer you're adding additional requirements to the project chat were originally cut because of cost constraints. C. Inform the customer that the project is completed and has come in under budget. D. Bill the customer for the full amount of the contract as this was the original agreed-upon price.
You know that PV = 475, AC = 430, EV = 480, EAC = 40, and BAC = 525. What is VAC? A. 440 B. 390 C. 485 D. 435
Explain the meaning of management.
You are a project manager for Picture Shades, Inc. They manufacture window shades for hotel chains that have replicas of Renaissance-era paintings on the inside of the shades. Picture Shades is taking their product to the home market, and you're managing the new project. They will offer their products at retail stores as well as on their website. You're developing the project schedule for this undertaking and have determined the critical path. Which of the following is true? A. You calculated the most likely start date and most likely finish dates, float time, and weighted average estimates. B. You calculated the activity dependency, and the optimistic and pessimistic activity duration estimates. C. You calculated the early and late start dates, early and late finish dates, and float times for all activities. D. You calculated the optimistic, pessimistic, and most likely duration times and the float times for all activities.
Which of the following brings together a set of tools and techniques used to describe, organize, and monitor the work of project activities? A. Project managers B. Guide to the PMBOK C. Project management D. Stakeholders
What is one of the most important skills a project manager can have? A. Negotiation skills B. Influencing skills C. Communication skills D. Problem-solving skills