how much quantity of cement and sand required for
construction of 10 cum brick work( Brick size
3"*4"*9"(Standard size ) an d for 10 cum construction of SSM
(Size stone masonary) with Cm 1:6 for both.
Answer Posted / ar. g.s. rehal
Let the size of brick be 230mm x 115mm x 75mm
Vol. of brick( w/o mortar) = 0.00198 cum.
Thk. of mortar be 12mm.
vol. of brick with mortar = 242mm x 127mm x 87mm
= 0.00267 cum.
No. of bricks in 1 cum. with mortar = 1/0.00267
= 373.99
Say = 374 bricks.
volume of 374 bricks= 374 x 0.00198 = 0.74052cum
Cement Mortar required for 1cum = 1 - 0.74052cum.
= 0.259 cum.
Say 0.26 cum
Add 15% for frog filling and wastage while execution.
.26 x 15/100 = 0.299 cum
Vol. of wet mortar = 0.299 cum.
Vol. of dry mortar( increase by 30% ) 0.299 x 30/100 =0.0897
0.299 + 0.0897 = 0.388 cum.
For CM of 1:6 (1 + 6 = 7)
Qty. of cement for 1cum = 1/7 x 0.388
= 0.055 cum.
Qty. of sand for 1cum = 0.055 x 6
= 0.330 cum.
Qty. of cement for 10cum =10 x 0.055
=0.55 cum.
Qty. of sand for 10cum = 10 x 0.330
= 3.30 cum.
| Is This Answer Correct ? | 89 Yes | 24 No |
Post New Answer View All Answers
suppose we have a tendency to make a hole on the surface of the simple supported beam, than where we goes to make it?
what will happen if one could not properly follow the spacing of slab reinforcement bar?
how much st. steel is required for staging of concourse slab of a elevated metro station allowing through traffic .
Pls help me to arrive the rates for centering shuttering for highbay using H-frames?
What is different between DI Pipe and CI pipe?
Bernaullis theorem deals with the law of conservation of mass momentum energy none
What is the withdrawal force of steel nails?
Why should appointment store person for project ? what is the benefits for company ?
what is the cost of rcc roof casting of 400 sq. ft. in kolkata
What tor stands for in tor steel?
For what purpose bedding is used under storm water drains, explain?
I used Etabs software to analyse a high-rise building. And I want to use templated UBC-codes inside to calculate the Seismic load. My question is: whether or not I have to control the seismic load by base shear load which is manual calculation? (just for more clarification: I can control this by input the scale factor into Eartquake definition in Etabs) I would highly appreciate your answer.
how do you calculate the length of "L" of main & distribution bar for reinforcing of raft footing
how to calculate freeboard in under ground water tank and technical details
how to do cementicious paint for rcc walls of cw pump house