Is there a way to know the aprox shuttering qty if vol of
concrete is known? any thumb rule?
Answer Posted / dushyant bansal
Generally for high rise building shuttering is taken as 3.5
times of floor area
but in case where there are Post tension slab the ratio is
taken as 3
| Is This Answer Correct ? | 6 Yes | 1 No |
Post New Answer View All Answers
Trapezoidal section footing calculation of Volume & its Area
How will be cutting in timber plate size 600*400 column size
What is the effect of a building collapse?
What are the responsibilities of a site manager?
how many running meters in one kilogram of 4mm pvc coated chainlink fencing
what is cement wastage percentage in NHAI ROAD WORKS
When was the first motorway built in england?
What is the purpose of Chipping in the heavy foundation?
What is the strength of cement?
wat would be the probable interview questions and GD topics for IOCL exam?
what is the types of door's wood?
trapozidal
how do you calculate the quantity of steel,cement for plinth beam. (example size 41'*0.58'*1.08')
Why do you want to work here
How to measure the requirement of cement n sand for 12mm and 20mm plastering thanks in advance