You are the test manager starting on system testing. The
development team says that due to a change in the
requirements, they will be able to deliver the system for
SQA 5 days past the deadline. You cannot change the
resources (work hours, days, or test tools). What steps
will you take to be able to finish the testing in time?

Answer Posted / neelima

1. priortise the tests based on the requirements
criticality,complexity, end user stressed .
2. check with the developers about what requirements are
going to be changed and how many tests are going to be
effected due to that.
3.check with the project manager to defer any of the
functionality testing for later .
4. check with the developers how thorough that their
modules are tested .

Is This Answer Correct ?    5 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What are the main key components in Web applications and Client Server applications? and their differences?

1485


What is the test case?

636


what are the test bugs

1485


How quickly we need to fix the bug? Or how soon the bug should get fixed?

698


hi... guys can any one pls help me out.... I m civil engg graduate i want to come into s/w field... i have decided to do manual testing course. i know its not sufficient.. which r the other coures shall i do with this.. suggest me good atomation tool and SAP courses... thanks in advance.. i wil be thankfull to u all

1690






Hi, Anybody knows about Hexaware company..

1663


How do you estimate white box testing?

658


How do you scope,organise and execute a test project.

1642


1.How can you Pick Integration Test Cases? 2.When will you start Regression Testing? 3.What is the difference between QA & QC? 4.When Will you Exit In Testing? 5.Test Deliverable's 6.What is the difference between windows based appln and web based appln? 7.What are the types of regression testing?

4459


hi friends .......... from srs to signoff what r the tests the testing team will conduct either sequentially or parallel pls advice thanks in advance

1446


Hi All. How can we write negative test cases for Logout Operation ? Please place the answer with a few details and if possible add some related object properties. "A tester exposes his/her ability not only by words he/she also proof it by work"

2497


Could some one tell me test cases for multi line text boxes like Notes field?

1688


What is the typical situation u faced while collecting the test data?

1645


I have 2 yr Localisation testing exp now i want to job in MNC My manualtesting knowledge+2 yr exp sufficiant for in MNC

1574


Is compatabilitytestig and port testing are same

1458