Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

You are the test manager starting on system testing. The
development team says that due to a change in the
requirements, they will be able to deliver the system for
SQA 5 days past the deadline. You cannot change the
resources (work hours, days, or test tools). What steps
will you take to be able to finish the testing in time?

Answer Posted / neelima

1. priortise the tests based on the requirements
criticality,complexity, end user stressed .
2. check with the developers about what requirements are
going to be changed and how many tests are going to be
effected due to that.
3.check with the project manager to defer any of the
functionality testing for later .
4. check with the developers how thorough that their
modules are tested .

Is This Answer Correct ?    5 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is 'Account Conditioning'?

4482


Test cases for Internal IP Messenger

4820


What is bug leakage?

1186


Usually customers won’t give all the requirements. How will you manage & collect all the necessary information?

1204


what is diffrence between dynamic black box testing and dynamic white box testing

2004


What is common interface?

1954


Write positive and negative test cases for forgot password?

4867


What is the difference between IE, Opera & Mozilla Firefox in web Testing and which brower will think that is much better?

2083


What are the Major Functionality for a ATM machine ??

5979


Can you do system testing at any stage of sdlc?

1185


how will you estimate of your website?

2093


Hi, I want "Intergraph" placement papers for experienced people which was conducted recently in Hyderabad. Thanks, Purnima.

2409


1) Test summary contains ? 2) Requirement Tracebility means ? 3) Test Effort contains ? 4) Test Planning Productivity ? 5) Metrics should be caluclated ? 6) Interest rate Rsik is a type ? 7) Test analysis and Design process task? 8) secured loan is a part of Liability (or) assest in a balance sheet? 9) Money Market means? 10) a ------ specifies all of the terms of a loan and the obligations borrower ? 11) what is a primary market is ? 12) Quality of Testing measure with ? 13) Company has a share with facevalue 10 rs/- and NAV of 37 after comapny has given Dividend of 35 % then How much NAV become ? ( I don't know what is NAV means, question overall Idea I am giving not 100% perfect ) the potions for these are 1) 33 2) 33.50 3) 37 4) 42 14) one compay has taken 10 million loan from a bank for a Interest rate is 10 % and base amount is 0.4% so how much they had paid monthly Emi ? they provideansews like 1) 100000 2) 114000 3) 140000 4) 104000 Remaing questions I not remember.

2722


What is Independant Testing? When and where this type of testing will be performed?

1993


What is the difference between pilot and beta testing?

1186