In both cases you are using a wet leg configuration with the
DPT. In the steam drum if you use the old fashion way by
changing the HP and LP legs around you will get a positive
mmH2O reading. If you use a piped SMART Tx or a SMART
capillary type DPT, you will get this negative mmH2O readings.
I have already done a writeup on this so go and look at
previous questions.
In the deaerator there is a vacuum but again the same wet
leg is done. I have already done a writeup on this vacuum
applications as well so go and look at previous questions.
Good luck
Is This Answer Correct ? | 7 Yes | 30 No |
Post New Answer View All Answers
what is the imbustion control loop
List three types Level Gauges with their working principles
Valve positioner and actuators in detail.
How to work temperature gauge?
what is function of SCADA , and how is it work, explain with difination
what is the calibration procedure for transweigh make weigh feeder?
HOW TO CALCULATE ACCURACY OF AN INSTRUMENT. WHICH IS COMPITABLE FOR USE.
how will you check torque value during Factory acceptance Test for control valve/ESD ON/OFF VALE how will you confirm this torque value is being correct, Which document will you be refer.
how does we calibrate a square root flow transmitter ,give an example and explain it step by step like range calculation , calibration hook up series connection , zero check , and how to apply pressure , and if not geting proportional output then what should we do ?
how many types of viberation transmitter and how to calibrate and where use of vibration transmitter
To become an Instrument DESIGN engineer, is there any softwares or training to become Instrument Design engineer, plz suggest me, Iam very much interested in designing.
Name different parts of a pressure gauge.
how to calibrate 0- 150 psi presure gauge by dead weght tester
Specify eight technical requirements that you would consider important, when deciding upon a particular control valve?
What are continuances of connecting earthing and shield of branch cables (instrument to Junction box), at the same earthing pot provided on JB? Is it ok, or may produce some problem?