Can you explain about actual GI (gods issue) date and
planned GI date? Can actual GI date differ from planned GI
date?
Answer Posted / siva
I believe the actual GI date can differ from Planned GI
date..See u plan to make a GI on one date and the process
gets delayed due to sudden deficiency of the material as
some might be identified as defective at the last minute..
the organisation would like to have a watch on this thats y
we give two different dates.. Pls correct me if im wrong..
| Is This Answer Correct ? | 9 Yes | 4 No |
Post New Answer View All Answers
1. Credit Control Area can be mapped to Sales Area and Company Code. To which systems gives priority? 2. Whether Credit Memo request will be generated only when Rebate agreement tgt amount is achieved? 3. How to have different Pricing procedure for a Billing Doc and Credit Memo Request? 4. Credit Memo request to Credit Memo: what are the accounting entry changes? 5. Copy Control: Significance of Assignment option? 6. One time customer: How system will react while creating Order using one time customer?
Can you make texts mandatory for a customer master or a sales document?
What is a sales organization?
can some body give me some idea on integrations of sd and sap crm service
what are the sales document types in sap? What is the configuration step to define sales document type in sap sd?
How do you create sales organisation?
What does the term “business area” refer to and how can it be used?
PRICING…… I have a requirement where I have a fright condition which is a header condition for the whole document, I will be maintaining the fright condition recorder (header level) because it’s header condition, now the requirement is if I want to have 5 conditions to be calculated for each item because let’s say I have 5 line items, I want to see how the side calculated first of each item so what’s the best way to take out that out of the system in standard configuration, how can we achieve this?..... REPEATING question (I have a fright condition, now fright condition is a header condition, now my requirement is I wanted to applied that fright condition each line item level so fright condition applies a header level but my requirement is I want to see each and every line item should also get this fright condition on the value of the item, let’s say my fright is $100 so I have 5 line item, each item has the 10 10 10… so build on that value I want to purpurnate the fright condition, how can we achieve this from the standard system configuration stand point?
What is a company?
Differentiate between shipping point and loading point.
A Client wants to connect his SAP ECC system to his SAP CRM system. What do you want to do to enable the integration?.
In how many ways a sap system can interact with third party system. please provide the details to understand well about interfaces
For the 1st 10 sales order I want to give discount, so what customization we have to do with?
If the recruiter asks that are you involving any project ? Because I have shown in my resume that I am in "Offshore post implementation support IN SAP SD module"and this is not real. So I want to know if this question arrise then how can I properly describe my involvement in the project and what will be my responsibility in it???? THANKS IN ADVANCE
I was faced these interview questions, please provide answer with your real life experience SAP gurus. 1. As a SAP SD consultant how did you integrate/interact with MM and FI/CO? 2. Tell me about your OTC process expreience? 3. How have you used MASS tool in your last project, and to upgrade what data? 4. Tell me about your EDI/IDOC experience? PLease answer any/all questions as per your wish. Thank you very much in advance, god bless.