DG B-check,C-Check,D-check is depending upon the running
hrs.If the running hrs is not reached as mentioned.How to
conduct the DG checks.
Answer Posted / arunselva
A Check Daily check
B Check 250Hr to 300Hr or 6 Month
C Check 1000Hr or 1Year
D Check 1500Hr or 2Year
| Is This Answer Correct ? | 57 Yes | 20 No |
Post New Answer View All Answers
Define the overload capacity of the motor?
I am inpecting a 10kVA UPS what tests should i do and should i observe?
Is there any rule to select the voltage of motor based on KW rating? What is the rating above which lt motor becomes the HT motor?.
How to design harmonic filter at the project stage without nowing the harmonics levels
How isolater function when installed inelectrical 440V wiring
What is the control action?
what is difference between 2 pole structure and 4 pole structure in transformer yard
When calculation of fault current and fault Kva is to be done,why always we use per unit value and why we consider the base kva?
how to calculate the surge level of surge suppressors related to the SF6 cicuit breakers?
clarify types of motor operated valves and advantages
hi frds, i m electrical engineer.can i get cdr for electrical engineer if u have then send me on my mail id its jayesh_ee88@yahoo.com.please help me frds
How to findout raw or ups power? its not indicated in socket,
why dc is used in control circuit for mv & hv switchgear instead of ac
What is EHT tariff or Power factor Tariff ????
i have applied for the post of RRB section engineering chennai board please send me previou papers and solved answer. my mail id jagarapusrinivas@gmail.com