Do your single-level BOMs represent production levels and do
you keep your BOM header materials in stock? If not, do you
produce non-stock items, or are some assemblies just used as
structural elements in a BOM?
Answer Posted / nvt
Yes
We can use the phantom material which is not produce but
have a stuctural element in the BOM
Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
what do you mean by planning time fence
What do we do in realization phase?
What is the data you give in SOP
What is meant by payscale structure? How did you configure the payscale structure?
what are the problems you faced in MRP?
What is the planning horizon?
What is MRP procedure
What is the difference between stock transport order and stock transfer order?
what does SAP business workflow do?
suppose we have sales order-40, PIR-25,warehouse stock-40, so when we run mrp,what quantity the system displays with MTO & MTS. How?
How the process time is calculated in a wc when both labour, machine categories exist?
After doing realization how we will check whether it is working or not?
If u maintain sub-contacting where and how will be reflect
What do you mean by pooled capacity?
What is the Difference between TECO and CLSD?