plz give me the rate of RCC(1cuM), PCC(1 cuM), Brick Work
(1sqM)?
Answer Posted / siva rami reddy
Hi,
Question is not correct. RCC or PCC cost will be depending
upon the grade of concrete. If PCC is M10 (1:3:6) and if it
RMC (Ready Mix Concrete) cost will be about 3500 Rupees per
Cum and RCC of M20 or 25 cost may not differ much may be
around 4250 more or less. Brick cost will 3000 Rupees per
Cum.
Is This Answer Correct ? | 90 Yes | 18 No |
Post New Answer View All Answers
how to preaper for interview wat they asked in interview give me idea
Define What are the uses of alloys in daily life and how are alloys made?
hi, i am appearing in HPCL(CIVIL ENGG.)exam. plz send me placement paper of this exam if u are having
As we know that steel is a tension member but why we are using STRUCTURE STEEL as a COLUMN (Without concrete) where column is a compression member and compression strength of steel is very low
give me the rate analysis for Bituminous Macadam and SDBC
how ratio is calculated for any grade of concrete. for e.g. sppose M20 requires(x;y:z) quantity of cememt sand and aggregate.
What is the strength of 1:6:12 mix?
rcc floor to floor 4m. in column reinforcement where we provide lap in exact location.
What is quantity of cement and sand required for 2000sqft of tiling?
How to arrive the co- efficient of all civil activities? For ex:- painting-enamel in wooden doors. co efficient is 1.8. How this is calculated
what is conventional shuttering rate per square feet of built up area? what is Mivan shuttering rate per square feet of built up area? what is coupler shuttering rate per square feet of built up area?
How can calculate the requirement of steel bars of rcc slab for 1100 sq ft?
What goals do you have in your career?
which software is better for design and analysis of buildings (stadd pro ) or (Etabs)
what is the design procedure for building