my scenario is repetitive manufacturing (REM) make-to-stock
(MTS)production for sugar industry. What are the things, I
have to customize for this scenario, to the PP point of
view..

Answer Posted / jinchandra

First of all make PP master data,before that create your
orgnisation structure,
After that go as bellow,
In material master view SELECT REM ALLOWED,
IN CUSTOMIZING [OPP3] SELECT THE REM PROFILE,
AGAIN IN MRP4 VIEW CREAT PRODUCTION VERSION BY USING TRSN
CODE C221.
CARRY OUT BATCH MANAGEMENT ,BATCH ASSIGNMENT, PP-PI SHEET,
MASTER RECEIPE,
go for product cost collector KKF6N,

Is This Answer Correct ?    5 Yes 4 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Mention what is the t-code for changing production order and to display production order?

635


What are all the ‘technical types of bom’?

632


Difference between standard cost and variable cost.

1834


What do we do in realization phase?

676


what do you mean by planning time horizon

550






Explain what happens to plan after it has been converted into production order?

612


Differentiate ‘variant bom’ from ‘multiple bom’?

652


Scheduling times can be defined in the material master record by?

591


Explain Availability check.

923


What is group bom?

730


What is the difference between the fixing type 1, 2, 3, 4?

5162


What is Material status and which view of the material master it is available?

1011


What is the use of mrp group?

644


What is Inspection Points?

1011


What are the keyfields found in mrp view 1?

582