Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

my scenario is repetitive manufacturing (REM) make-to-stock
(MTS)production for sugar industry. What are the things, I
have to customize for this scenario, to the PP point of
view..

Answer Posted / sundhu

Hi,
To customize this first need to maintain the Master data,
1) Material Master-> MRP4-> create & add Producion version,
2) Define the BOM-> CS01.
3) Create a Rate Routing->CA21.
And in Transaction data,
1) Create a Planned independent Requirements->MD61,
2) Run MRP->MD02,
3) Review the capacity through Planning Table->MF50,
4) Finally can create the Product Cost Collector->KKF6N.
Note:
KKF6N is a integration between PP & FICO.

Is This Answer Correct ?    7 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Explain the mrp controller and their uses.

1239


What is detail scheduling

1769


What is collective order. Pre requisite of the collective order?

2797


What is recursive BOM

1602


Different types of Object Dependencies.

1490


What is the use of plm (product lifecycle management) in sap pp?

958


Define mrp group

1044


What is sap pp?

1112


What is the uses of production scheduling profile and what the configure have you done current project

2066


What is the use of infogroups?

1050


Which BOM item category you have used?

1481


Describe the process for creating and adding to material BOMs. Include release procedure/status, notifications, responsibilities, authorizations, involved systems, Engineering Change Management, and so on.

1961


Do you have any idea about Capacity Planning?

1923


Two or three Production Orders are there for the same day, and goods are not sufficient and then how to proceed?

1626


How can you get planned orders scheduled so that you can do capacity leveling ?

1049