my scenario is repetitive manufacturing (REM) make-to-stock
(MTS)production for sugar industry. What are the things, I
have to customize for this scenario, to the PP point of
view..
Answer Posted / sundhu
Hi,
To customize this first need to maintain the Master data,
1) Material Master-> MRP4-> create & add Producion version,
2) Define the BOM-> CS01.
3) Create a Rate Routing->CA21.
And in Transaction data,
1) Create a Planned independent Requirements->MD61,
2) Run MRP->MD02,
3) Review the capacity through Planning Table->MF50,
4) Finally can create the Product Cost Collector->KKF6N.
Note:
KKF6N is a integration between PP & FICO.