Answer Posted / sjtbehera
you are given 3”x4”x9” standard size of bricks
After placing mortar it became- 4”x5”x10” =
10.16cmx12.7cmx25.4cm
No of bricks are required=
10/.106x.127x.254=3069 nos
The size of brick without mortar= 3”x4”x9”=
7.62cmx10.1cmx22.8cm
Then net mortar required =10-(3069*.076*.101*.228)
= 4.62cum
Due to frog filling, brick bonding course and
wastage add 15%
Volume of wet mortar= 4.62+4.62x15%=5.30cum
When dry increase this qty. by 1/3rd=
5.30+5.30x1/3=7.06cum
Ratio is =1+6=7 cement = 7.06/7= 1.06 = 29 bags
Sand= 7.06*6= 42.36cum
| Is This Answer Correct ? | 47 Yes | 54 No |
Post New Answer View All Answers
What is oneside mat. And explain
why top layer of block work shoud be full size if any cut block adjustable than another layer?
Pls provide me with the calculation or codes related to de- shuttering of flat slabs
What are the uses of groynes?
What is the basic difference between OPC
how to tie 10 legged stirrups
What are the problems one might face while having a Cantilever balcony?
what is pile and deam foundation
When was the first motorway built in england?
PCC Road Min Grade M 30 for VR standard Mahatashtra load 30 KN. what should be thickness of pavement, width 4m what should be length of panel.
What is Architect-Prepared Contract?
How to find weight of steel in kg if we know the area which is in m2? Following details are known to us, Area=125m² thk of slab=250mm Steel details:T12@200 PS:considering mesh top and bottom with X and Y direction
Rate analysis for construction of a solid block masonary of size 400x200x200 in C.M.1:5 in superstructure .Compressive strength 5.00 N/Sq.mm Confirming to IS: 12894:1990, with necessary scaffolding, raking of joints and pointing the same. I require rate per Cum.
asubmerged weir is one in which the water level on the down stream side of the weir is just at the crest level below the crest level above the crest level at stamp elevation as water surface on upstream
What Reinforcements Are Used In The Process Of Prestressing?