Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how much quantity of cement and sand required for
construction of 10 cum brick work( Brick size
3"*4"*9"(Standard size ) an d for 10 cum construction of SSM
(Size stone masonary) with Cm 1:6 for both.

Answer Posted / sjtbehera

you are given 3”x4”x9” standard size of bricks
After placing mortar it became- 4”x5”x10” =
10.16cmx12.7cmx25.4cm
No of bricks are required=
10/.106x.127x.254=3069 nos
The size of brick without mortar= 3”x4”x9”=
7.62cmx10.1cmx22.8cm
Then net mortar required =10-(3069*.076*.101*.228)
= 4.62cum
Due to frog filling, brick bonding course and
wastage add 15%
Volume of wet mortar= 4.62+4.62x15%=5.30cum
When dry increase this qty. by 1/3rd=
5.30+5.30x1/3=7.06cum
Ratio is =1+6=7 cement = 7.06/7= 1.06 = 29 bags
Sand= 7.06*6= 42.36cum

Is This Answer Correct ?    47 Yes 54 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is oneside mat. And explain 

2539


why top layer of block work shoud be full size if any cut block adjustable than another layer?

2142


Pls provide me with the calculation or codes related to de- shuttering of flat slabs

6791


What are the uses of groynes?

1077


What is the basic difference between OPC

1999


how to tie 10 legged stirrups

6501


What are the problems one might face while having a Cantilever balcony?

1511


what is pile and deam foundation

2295


When was the first motorway built in england?

1032


PCC Road Min Grade M 30 for VR standard Mahatashtra load 30 KN. what should be thickness of pavement, width 4m what should be length of panel.

2514


What is Architect-Prepared Contract?

1140


How to find weight of steel in kg if we know the area which is in m2? Following details are known to us, Area=125m² thk of slab=250mm Steel details:T12@200 PS:considering mesh top and bottom with X and Y direction

3054


Rate analysis for construction of a solid block masonary of size 400x200x200 in C.M.1:5 in superstructure .Compressive strength 5.00 N/Sq.mm Confirming to IS: 12894:1990, with necessary scaffolding, raking of joints and pointing the same. I require rate per Cum.

2507


asubmerged weir is one in which the water level on the down stream side of the weir is just at the crest level below the crest level above the crest level at stamp elevation as water surface on upstream

1910


What Reinforcements Are Used In The Process Of Prestressing?

1291