Method of findingthe dry ingredient quantity of 1 m3
concrete.
Answer Posted / naresh thakur
soppose, concrete mix ratio = 1:1.5:3
then, sum = 1+1.5+3 = 5.5
as we know,dry material required for 1 cum. of concrete =
1.54 cum.
then we can find -:
(1) cement = 1*1.54/5.5 = .28 cum. or .28cum.* 28.8= 8.06
bags.
(2) sand = 1.5* 1.54/5.5 = .42 cum.
or .42cum.* 35.3 = 14.83 cubic feet.
(3) coase aggregate = 3* 1.54/5.5 = .84 cum.
or .84 cum.* 35.3 = 29.65 cubic feet.
so, dry ingredient quantity required for 1 m3 of concrete-:
cement = 8.06 bags.
sand = 14.83 cft.
coarse aggregate = 29.65 cft.
do not forget to add 5 to 8 % addition matreial.
| Is This Answer Correct ? | 347 Yes | 36 No |
Post New Answer View All Answers
Formula of area of crane hook
how to read the drawings to find the quantity of steel in a storm water manhole or any other structure?
Define What is the origin of name Railway Sleepers?
How will be cutting in timber plate size 600*400 column size
please what is the number of bars required for a column of 6mx6m and 450mmx300mm,its a commercial building (Church)
how to compute slab reinforcements on step by step procedures??
what s the standrd size of pvc fittings ,like elbow, bend,tee etc ? please explain with figure ?
Which are the Steel tests ?
what is the cost of rcc roof casting of 400 sq. ft. in kolkata
What is meant by solid geometry?
What Are The Steps Involved In The Concreting Process, Explain?
load combinations how many types for staad design purpose?
Aptitude, reasoning, quants, verbal and technical question
How to calculate quanty of steel in four leg stirrups?
I am doing a engineering contract with GOI. I have purchased certain material from outside Maharashtra and paid CST on that material @ 5.25%. Please intimate whether I will be liable for VAT or VAT on works contract or not.