Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

WHAT IS THE DIFFERENCE BETWEEN SHOP DRAWINGS/ DESIGN
DRAWINGS AND AS BUILT DRAWINGS??

Answer Posted / prashant

When we are qouting for a project its on the basis of
TENDER DWG
After that we start prepearing the SHOP DWG ie for use at
site and as per this dwg work has to be executed at site
Finally we have to prepare the AS BUILT DWG ie the exact
dwgs as to how the work was carried out at site bcoz at
site due to the site conditions the site engg mite have
laid the wire or the conduits thru a diif path as shown in
the shop dwg. All such deviations are to be shown in the AS
BUILT DWG

Is This Answer Correct ?    53 Yes 8 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

In constant power region of 3-phase IM torque-speed characteristics, if frequency increases slip A does not alter B decreases C increases D none of above

2051


When the relative speed between the magnetic fields of stator and rotor does is zero under steady state operation?

1265


what's producer of XLPE cable laying in undergroung

2125


Is it required to do earthing in 2nd shop if earthed armoured cable is laid from 1st shop ?

1917


What is bridge rectifier and explain with details

1912


What is minimum phase system?

1132


Convert a star connected network into a delta connected network.

1110


CALCULATE THE TOTAL VOLTAGE DROP AND SELECT THE CABLE SIZE IN MM-SQARE FOR A PANEL-262KW AT 110 METER FROM THE SOURCE SUPPLY , SUPPLY VOLTAGE 240/415

2642


state the disadvantages of carbon filament???

2934


while doing high voltage test on 11kv/433 distribution transformer why we only give 28 kv on hv side and 3kv on lv side for power transformers what is the value what factors it depends

2850


why we are not giving the zone 1 trip command to the master trip relay

1725


Explain the method to keep noises low in a control system?

1126


What is the effect of positive feedback on stability of the system?

1640


Hi Everyone ! My Name is Hakim ullah khan please i need formula of Cable Rating because i want to calculate by self without check any Table Chart... Thank you.....

1702


What products have you designed which have entered high volume production?

2058