Answer Posted / rajani
Actually DG size has to select depends on maximum demand
and considering base load and starting load and step load
base load = total maximum demand - loads which are
taking high loads at startign
starting load = if motor loads are DOL starts 6 times to
the Ifl will take at starting and soft
starters /VFD's will take 3 times to Ifl
step load = Whwn the main power supply is off
immidiently what are the load we can
switched ON through DG -called step load
(generally 40-60% of Dg load can be ON as
first step)
So our selected DG shopuld meet the step load and capable
to withstand startign loads
| Is This Answer Correct ? | 12 Yes | 5 No |
Post New Answer View All Answers
what can be the causes of capacitor start motor having a higher current that its actual
What is the method to solve circuit using source transformation?
If we have to feed a housing complex having load 8MVA, than what would be the better option, either we first step down 33kv supply into 11kv & than 430v or we proposed no of 33/.44 kv transformer, also which option is economical?
how to produsing geretor power
What are the necessary components of the feedback control system?
What is the pro & con of having 11kv & 33kv incoming, and what is the adv & disadv. of converting from 11kv to 33kv.
all interview questions with answers of ntpc (2000-2009
I want formula to calculate current loss with distance in km.I searched many sites but didn't right answer.Plz reply me
why ten delta testing is carried out on power transformer
we use capister for power factor. when we use capaciter in dg circuit than defect dg. can we use capaciter bank for dg circuit
various transmission tower like .,D tower ,K.C.O tower ,C.C.O tower,K.C.R tower ,C.C.R tower ,H.C.O tower in different tons.
In power transmission using open belts or horizontal shafts it is preferable to have the slack side of the belt on the top because
If a current -8+6sin6t is flowing three ammeter, one is a centre zero PMMC meter, one is true rms meter and one is moving iron meter. What are the reading of these three meter respectively?
how can service sitting be setted for MCCB?Example for sittings IR (CURRENT RATING),IS(CURRENT STARTING)IO (current operating
how wecalculate breaking capcity of acb mcb mccb .explain with example