Answer Posted / rajani
Actually DG size has to select depends on maximum demand
and considering base load and starting load and step load
base load = total maximum demand - loads which are
taking high loads at startign
starting load = if motor loads are DOL starts 6 times to
the Ifl will take at starting and soft
starters /VFD's will take 3 times to Ifl
step load = Whwn the main power supply is off
immidiently what are the load we can
switched ON through DG -called step load
(generally 40-60% of Dg load can be ON as
first step)
So our selected DG shopuld meet the step load and capable
to withstand startign loads
Is This Answer Correct ? | 12 Yes | 5 No |
Post New Answer View All Answers
what is p.s impedance measurement test in earthing transformer?
what are the sample questions asking to the test cunducting for electrical superwising lisence test?
what is meant by twilight switches 7 where its applicable ?
How does cost of generation from hydropower plant compare with other sources of electricity?
why we r not earthed Control cable of C.T. terminals
Brief working principle of stabilizer,application & safety precautions
any application of back emf
what is feed back and what are feed back amplifiers?
hr round
what are the accessories need to be added while doing estimation for the following: 1.MCCB 2.MCB 3.ACB
how technical is calculated in 11kv line and lt line
what happend to DC shunt motor if its field winding insulation becomes slightly weak? will that motor can run on full load or not explain in detail. thanks
Difference between field rheostat and armature rheostat.
difference between ac series and parallel circuit
The advantages of Magnetic flux leakage technique over Ultrasonic technique for non distructive testing of material.