What is the max demand on your transformer and your company?
Answer Posted / will
Maximum demand means that it shall not cross the 100%
rating of the transformer, if the transformer has no
colling stages and can take extra demand.
Normally the cooling stages increase the transformer
capacity to take load 33% more at eact cooling stage.
Ist cooling stage FA-1.33%
2nd cooling stage FA-1.66%
That means when the transformer getting loaded more than
100% capacity the ist cooling stage gets automatically on
and when it gets more than 133% loaded the second cooling
stage gets automatically on.
| Is This Answer Correct ? | 4 Yes | 11 No |
Post New Answer View All Answers
CPC cable .PVC \1C....I want to get sure that type is flexible indoor or to be install on trench. please advice .thanx :)
which protection function should measure RMS value of current&DFT value of current?
Explain bypass capacitor?
what is smart grid? why we use it? explain in detals bcoz i want give presentatin from it....
Why do we use center tap transformer that used with portable tools
What is the necessary condition for stability.
What is the difference between electronic regulator and ordinary electrical rheostat regulator for fans?
why we r not earthed Control cable of C.T. terminals
What is different type of Electrical curve and how it protects the equipment's while up-normal situation?
Define damping ratio.
why is the power generator connected as star earthed or star earthed through reactance and what its features ?
we are small scale industry in production of rice & rice bran. Pls let me know how to take contract demand for our industry.. (for information we have total 600.hp)
why should the primary of transformer be connected in delta in a heat run test?
What is electrical diversity factor in electrical installations?
We are preparing another project which involves Waste heat recovery from a 1 MW GE Engine. The Engine in particular gives out flue gas at 487Deg C with a flow rate of 5650 kg/hour and this can be cooled to 180 Deg C. This gives a thermal output of ~ 594 KW that is available for input to VAM via heat exchanger / boiler. Additionally 581 KW will be available from engine jacket water (temperature profile 80/ 80 Deg C and a flow rate of 50m3/hr) Our estimation is that 300 TR of cooling is possible with a suitable VAM machine(s). Please advise what is the most suitable arrangement with maximum TR and min Capital expenditure. plz reply me as early as possible