Answer Posted / sri
NEUPL-Regenerative Planning (Planning of all MRP-relevant
Materials)- the systems plans all the materials in a plant.
This is mainly useful for the first planning run or also
during day-to-day planning run if the data consistency
cannot be guaranteed
NETCH-Net change for total horizon( to execute MRP for only
those materials which have undergone MRP relevant changes.,
for eg., due to goods issue, new sales orders or changes to
BOM structure.)
NETPL-Net change planning in the planning horizon( planning
of all materials to which an MRP relevant change has been
made within the planning horizon, Planning within the
planning horizon)
| Is This Answer Correct ? | 26 Yes | 0 No |
Post New Answer View All Answers
What does the use of ms70 followed by mcec get you?
Consignment matl how will be use
What is scheduling
Which MRP types you have used?
How do I default it 41?
Suppose the client wants me the vacancy to be displayed on a website as well as ess. How should I do it?
What is 'mps' (master production scheduling)?
Why is work scheduling required for semi finished and finished products?
How to move to the realization phase?
What is internal payroll process?
Describe the process for creating and adding to material BOMs. Include release procedure/status, notifications, responsibilities, authorizations, involved systems, Engineering Change Management, and so on.
How requirements( pir, sales order, customer requirement) are reduced after they are produced?
What are the types of MIC?
What are the MRP master data?
• How are basic order dates determined?