What will u do if a background is running from 2days?

Answer Posted / rout

If u like to kill the job then go to.....
SM37->find the job->find job details->find out instance
number on which job is running.....then
SM51->select the job->select work pross->cancel without core

Is This Answer Correct ?    13 Yes 3 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What are the regular activities u do in solution manager and how

1622


How will u send mail after completion of backup?

1737


How to find users used transaction codes which are not authorized for?

1897


How client refresh is different than client copy?

714


Where will you change the parameters in three profiles?

721






What is sap ides?

629


The transaction should not be displayed in User Easy access menu. How to do user auditing in sap? What will u audit?

1980


Error in the phase import_proper while applying support packages?

1342


What is transport domain?

1414


Example you have 6 sap application servers, I want to monitor all the application servers. How to configure a CCMS?

2790


what is netweaver

1113


For ex: i scheduled one ABAP program as a background job but it was running 10 days, how to analyze the problem?

1439


dear friends, HOW TO CONFIGURE INTO ABAP WEB DYNPRO AND ADOBE OF ECC6.0 R/3 IDES SYSTEM?

4047


What is a support package? What is its purpose?

638


what is your project architecture?

1645