why we step down voltage level from 33kv to 11kv and 11kv
to 415v.Instead we can step down voltage from 33kv to 415v
directly using single transformer.
Answer Posted / anonymous
11kv is basically for primary distribution say to a large
factory. so at a substation, stepping down to 11kv for such
use and further stepping down to 415V for residential areas.
| Is This Answer Correct ? | 64 Yes | 21 No |
Post New Answer View All Answers
what is acceptance test in electrical engineering.
what type of questions are asked and howmwny questions belong this catagory?
1.why are not using acb 33kv ht side? is there any problem 2.what is difference between acb,vcb,sf6 breackers? 3.what is the function of invertor and convertor in ups?
in control panel, how can i measuring the distance between one bus bar to another bus bar. then now only for bus bar. in mpcb and contactor also. that means one mpcb to another mpcb how much distance? how can i calculate that.
What is meant by reset level of the relay?
What is an order of a system.
Dear All we are having a problem in G120 BOP showing alarm A0503, F0052, F0060 we can not remove fault alarm ,Please any body help us. kowsar
How to megger test 11 kV cable and the acceptance IR value
rajha power sector details
Why are the cores of large transformers built up of circular transactions ?
What is the formuala to calculate the rating of motor protection circuit breaker
Why line VTG = √3 phase VTG in star? How?
what are inherent currents?
what is a reactive power? what is the relation with power factor?