What is "Readjustig goal and Milestone" in project
managment and project planing
Answer Posted / rashmi ranjan sinha
Milestone: Date by which major activities are performed.
Readjusting: If the milestone seems not to be achieved as
targeted or incur a risk, it should be readjusted setting
goals with different approach.
| Is This Answer Correct ? | 17 Yes | 5 No |
Post New Answer View All Answers
You are a project manager for Dakota Software Consulting Services. You're working with a major retailer that offers their products through mail-order catalogs. They're interested in knowing customer characteristics, the amounts of first-time orders, and similar information. The stakeholders have accepted the project scope. Work has begun on the project, and you're confirming some of the initial work results with the stakeholders. You've asked for acceptance of the work results. Which process are you in? A. Quality Assurance B. Quality Control C. Scope Verification D. Performance Reporting
Which of the following processes assess the likelihood of risk occurrences and their consequences using numeric probability assignments? A. Qualitative Risk Analysis B. Risk Identification C. Quantitative Risk Analysis D. Risk Response Planning
What are the different project scheduling techniques?
All of the following are types of project closures or endings except: A. Addition B. Integration C. Verification D. Extinction
You are the project manager for a top-secret software project for an agency of the United States Government. Your mission, should you choose to accept it, is to complete the project using internal resources. The reason is because getting top secret clearances for contractors takes quite a bit of time and waiting for clearances would jeopardize the implementation date. Your programmers are 80 percent of the way through the programming and testing work when your agency appoints a new executive director. Your programmer’s are siphoned off this project to work on the executive director's hot new project. Which of the following addresses the purpose of Scope Verification in this case? A. It determines the correctness and completion of all the work B. It documents the level and degree of completion C. It determines if the project results comply with quality standards D. It documents the correctness of the work according to stakeholders' expectations
A project is considered successful when: A. The product of the project has been manufactured. B. The project sponsor announces the completion of the project. C. The product of the project is turned over to the operations area to handle the ongoing aspects of the project. D. The project meets or exceeds the expectations of the stakeholders.
You know that BAC = 375, PV = 300, AC = 200, and EV = 250. Variances that have occurred on the project to date are not expected to continue. What is the ETC? A. 75 B. 50 C. 125 D. 150
You are a project manager for a network cabling project for your organization. Your project team is made up of six full-time employees and three contractors. This is the first time they have all worked together. You know that the team will go through the stages of team development in the following order: A. Forming, storming, norming, and performing B. Storming, norming, forming, and performing C. Norming, storming, forming, and performing D. Forming, norming, storming, performing
You are developing your project schedule and have decided to use the PERT method to determine project duration. The estimates you've gathered so far include the following: Most likely is 200 hours, optimistic is 180 hours, and pessimistic is 220 hours. Which of the following is the correct PERT estimate? A. 190 B. 266 C. 200 D. 210
Your project is progressing as planned. The project team has comp up with a demo that the sales team will use when making presentations to perspective clients. You will do which of the following at your next stakeholder process. A. Report on the progress of the demo and note that it's a completed task B. Preview the demo for stakeholders and obtain their approval and sign-off C. Review the technical documentation of the demo and obtain approval and sign-off D. Report that the demo has been noted as a completed task in the information retrieval system
You are the project manager working on a research project for a new drug treatment. Your preliminary project schedule runs past the due date for a federal grant application. You adjust the schedule and find that two activities previously scheduled to start sequentially can be started at the same time. This is an example of: A. Crashing B. Fast tracking C. Resource leveling D. Adjusting the resource calendar
What are the triple constraints? A. Time, schedules, and quality B. Time, availability, and quality C. Time, money, and schedules D. Time, money, and quality
You are the project manager for a new website for the local zoo. You need to perform Quantitative Risk Analysis. You'll use all of the following tools and techniques to accomplish this except: A. Data precision ranking B. Sensitivity analysis C. Decision tree analysis D. Interviewing
The tools and techniques of Source Selection include all of the following except: A. Contract negotiation B. Work authorization system C. Weighting systems D. Independent estimates
What change would you like to bring in the management of your previous organization ?