What is "Readjustig goal and Milestone" in project
managment and project planing

Answer Posted / rashmi ranjan sinha

Milestone: Date by which major activities are performed.
Readjusting: If the milestone seems not to be achieved as
targeted or incur a risk, it should be readjusted setting
goals with different approach.

Is This Answer Correct ?    17 Yes 5 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

You are a project manager with technical expertise in the pharmaceutical industry. You've decided to try your hand at project management in the entertainment industry. Which of the following is true? A. You will likely be successful because communication skills are your strong suit. You anticipate having technical experts on your project team to address industry specifics that you're not familiar with. B. You will likely be successful because your organizational skills are excellent. You anticipate having technical experts on your project team to address industry specifics that you're not familiar with. C. You will probably be successful because you have a friend in the entertainment industry that has briefed you on all the important aspects of this project that you'll need to know. You anticipate having technical experts on your project team to address industry specifics that you're not familiar with. D. You will probably not be successful because you have little knowledge of the entertainment industry even though you anticipate having technical experts on your project team to address industry specifics that you're not familiar with.

569


Which of the following is true regarding the critical path? A. It should never be compressed. B. It allows for looping and branching. C. The critical path technique is the same as PERT. D. It's the duration of all tasks with zero float.

628


What type of organization experiences the least amount of stress during project closeout? A. Projectized B. Functional C. Weak matrix D. Strong matrix

637


You are a project manager working on a new software product. Your company plans to market to businesses. The project sponsor told you that the project must be completed by September 1. The company plans to demo the new software product at a trade show in late September and therefore needs the project completed in time for the trade show. However, the sponsor has also told you that the budget is fixed at $85,000 and cannot be increased by even $10 due to overall budget cuts this year. You must complete the project within the given time frame and budget. Which of the following is the primary constraint for this project? A. Budget B. Quality C. Time D. Schedule

608


You are a project manager for Dutch Harbor Consulting. Your latest project involved the upgrade of an organization’s operating system on 236 servers. You performed this project under contract. You are in the Closing process and know that product verification is for what purpose? A. To verify the goals of the project and assure the product of the project is complete B. To evaluate all the work of the project and compare results to project scope C. To verify all the work was completed correctly and satisfactorily D. To evaluate project goals and assure the product of the project meets the requirements

632






Your project progressed as planned up until yesterday. Suddenly, an unexpected risk event occurred. You quickly devised a response to deal with this negative risk event using which of the following tools and techniques of Risk Monitoring and Control? A. Risk management plan updates B. Workarounds C. Corrective action D. Additional risk identification

602


You are the project manager for a top-secret software project for an agency of the United States Government. Your mission, should you choose to accept it, is to complete the project using internal resources. The reason is because getting top secret clearances for contractors takes quite a bit of time and waiting for clearances would jeopardize the implementation date. Your programmers are 80 percent of the way through the programming and testing work when your agency appoints a new executive director. Slowly but surely your programmers are taken off this project and reassigned to the executive director's hot new project. Which of the following type of project ending is this? A. Starvation B. Extinction C. Addition D. Integration

705


You are a project manager who has recently held a project team kickoff meeting where all the team members were formally introduced to each other. Some of the team members know each other from other projects and have been working with you for the past 3 weeks during the Planning processes. Which of the following is true? A. Team building begins once all the members of the team are identified and introduced to each other. This team is in the storming stage of Team Development. B. Team building begins at the Planning process. This team is in the storming stage of Team Development. C. Team building begins once all the members of the team are identified and introduced to each other. This team is in the forming stage of Team Development. D. Team building begins at the Planning process. This team is in the forming stage of Team Development.

561


You’ve just accepted a new project management assignment. The project is for a customer in a foreign country. You've requested a business analyst and two other project team members from the country the customer resides in to participate on your team. The remaining team members are from your country. You know that the best way to ensure the project team doesn’t get bogged down in cultural differences and hold up project progress is to: A. Perform team-building exercises using videoconferencing to allow team members to get to know each other and get to the performing stage of team development as soon as possible. B. Provide diversity training for all the team members to make them aware of cultural differences and teach them to function effectively as a team despite these differences. C. Establish your role as project manager as the first order of business and require compliance to company policies. D. Require project team members to read and sign the organization’s diversity policy.

536


You are preparing a diagram that plots two variables, the dependent variable and the independent variable, to see the relationship between the two elements. What kind of diagram are you using? A. Cause-and-effect diagram B. Control chart C. Flowchart D. Scatter diagram

495


You are the project manager for a top-secret software project for an agency of the United States Government. Your mission, should you choose to accept it, is to complete the project using internal resources. The reason is because getting top secret clearances for contractors takes quite a bit of time and waiting for clearances would jeopardize the implementation date. Your programmers are 80 percent of the way through the programming and testing work when your agency appoints a new executive director. Your programmer’s are siphoned off this project to work on the executive director's hot new project. Which of the following addresses the purpose of Scope Verification in this case? A. It determines the correctness and completion of all the work B. It documents the level and degree of completion C. It determines if the project results comply with quality standards D. It documents the correctness of the work according to stakeholders' expectations

655


You are the project manager for a nonprofit organization. Your project has come about due to a social need. Your sponsor wants to get right to the Planning process. However, you know that a scope statement should be published prior to proceeding to the Planning processes. All of the following are true regarding scope statements except: A. It documents roles and responsibilities. B. It can be modified to reflect changes to the scope of the project. C. It describes the project deliverables, requirements, and objectives D. It serves as a baseline for future project decisions.

562


How to deal with underperforming team members?

588


You are going to take some performance measurements for your current project. You know that PV = 450, AC = 500, and EV = 375. What is the CV and SV respectively? A. CV = 125, and SV = 75 B. CV=-75, and SV=-125 C. CV = 75, and SV = 125 D. CV=-125, and SV=-75

707


You are a project manager and are in the Closing process of the project. Your customer has been presented with a formal acceptance and sign-off document. They refuse to sign, claiming the product does not meet their expectations. You know that this situation could have been prevented by doing all of the following except : A. Documenting the requirements B. Documenting the customer's refusal to sign C. Performing quality inspections during the process D. Requesting sign-off at important milestones

518