A company contracts to paint 3 houses. Mr.Brown can paint a house in 6 days while Mr.Black would take 8 days and Mr.Blue 12 days. After 8 days Mr.Brown goes on vacation and Mr. Black begins to work for a period of 6 days. How many days will it take Mr.Blue to complete the contract?
4 24909Post New OnMobile Interview Questions
How to use create planning book with two tables?
What is the difference between alt f4 and ctrl f4?
Which elements determine the enterprise structure for personnel administration?
How do you select a row using indexes in db2?
What will be the output of below code?
What is planning strategy you select to perform mts and mto? : supply chain management
What is an alias in tableau?
What operator is used to access a struct through a pointer a) >> b) -> c) *
What can be done with microsoft access?
What are the key features of ruby?
Can JQuery Run on MAC or Linux instead of Windows?
How can unintended consequences in AI behavior be avoided?
Tell us about an experience where you where you worked as a part of team.
Why LIC?
What is peoplesoft server process logs?