An IS auditor's MAJOR concern as a result of reviewing a
business process reengineering (BPR) project should be
whether the:

A. newly designed business process has key controls in place.

B. changed process will affect organization structure,
finances and personnel.

C. roles for suppliers have been redefined.

D. process has been documented before and after reengineering.

Answer Posted / guest

Answer: A

The IS auditor should review the redesigned process, assess
the risks, evaluate the controls and recommend the
inclusion, if appropriate, of additional controls. Whether
the changed process affects organizational structure,
finances and personnel, is a concern for the change
management team. The redefinition of roles for suppliers is
normally outside the scope of a BPR project. Choice D is an
important task but not as critical as a strong control
environment.

Is This Answer Correct ?    4 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

WHICH OF THE FOLLOWING IS OFTEN AN ADVANTAGE OF USING PROTOTYPING GOR DYDTEM DVELOPMENT

2838


purchase orders issued to vendors have been authorized as per the authorization matrix

1089